Municipal solid wasteOperatingFPC

Pinellas County Resource Recovery

Municipal solid waste power plant in Pinellas County, Florida. 76.5 MW of nameplate capacity across 2 generators, operated by Reworld Projects, LLC.

Also known as Covanta Pinellas Waste to Energy · EIA plant 50884

Analyst: free account, 1 question a day.

John Hopkins Middle S…BayboroTIA SolarLockheed Martin Solar SystemPinellas County Resou…10 km
Open in the map
6 plants within 19 km, from EIA coordinates.

Key facts

Capacity
76.5 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
January 1983First generator online
Operator
Reworld Projects, LLCEIA operator ID 55871
Grid
FPCBalancing authority FPC
Price nodes
None linkedNo verified ISO node
Location
Pinellas County, FL27.8733, −82.6741
EIA plant ID
50884EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Pinellas County Resource Recovery produces

Free · EIA-923

Net generation, 2025

339 GWh

339,033 MWh, final

Capacity factor, 2025

50.6%

2024: 55.6%

January to July 2026

60.8 GWh

Provisional

Range, 2015 to 2025

339.0–444.9

GWh a year. Low 2025, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000350,749Not reported12 of 12
2001331,386Not reported12 of 12
2002370,870Not reported12 of 12
2003409,938Not reported12 of 12
2004Not reportedNot reported0 of 12
2005439,116Not reported12 of 12
2006414,598Not reported12 of 12
2007406,155Not reported12 of 12
2008210,269Not reported12 of 12
2009330,776Not reported12 of 12
2010377,93656.4%12 of 12
2011371,94055.5%12 of 12
2012339,01150.4%12 of 12
2013340,70650.8%12 of 12
2014355,09953.0%12 of 12
2015357,64653.4%12 of 12
2016357,84253.3%12 of 12
2017400,67159.8%12 of 12
2018422,35563.0%12 of 12
2019444,94766.4%12 of 12
2020441,39665.7%12 of 12
2021427,70763.8%12 of 12
2022425,26363.5%12 of 12
2023428,24663.9%12 of 12
2024373,46955.6%12 of 12
2025339,03350.6%12 of 12
2026 (provisional, partial year)60,78515.6%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Municipal Solid Waste50.5January 1983
GEN2Municipal Solid Waste26.0April 1986

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Reworld Projects, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Pinellas County Resource Recovery and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Pinellas County Resource Recovery

Questions about Pinellas County Resource Recovery

How much power does Pinellas County Resource Recovery produce?

Pinellas County Resource Recovery reported 339,033 MWh (339 GWh) of net generation in 2025, a 50.6% capacity factor on 76.5 MW of nameplate capacity. From January to July 2026 it reported 60.8 GWh, which is provisional.

Where is Pinellas County Resource Recovery?

Pinellas County Resource Recovery is in Pinellas County, Florida, at 27.8733, −82.6741. It is in the Progress Energy Florida balancing area (FPC).

Who operates Pinellas County Resource Recovery?

EIA-860M for August 2026 lists Reworld Projects, LLC as the operator (EIA operator ID 55871). The operator is not always the owner.

When did Pinellas County Resource Recovery start operating?

Its first generator began operating in January 1983, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page