Natural gasOperatingMISO

Chickadee G-3

Natural gas power plant in Jefferson County, Texas. 34.8 MW of nameplate capacity across 5 generators, operated by Chickadee 3-G Purchaser LLC.

Also known as EIA plant 54321

Analyst: free account, 1 question a day.

HEB00048ExxonMobil Beaumont RefineryAir Products Port ArthurMotiva Enterprises Port Arthur RefineryChickadee G-310 km
Open in the map
6 plants within 31 km, from EIA coordinates.

Key facts

Capacity
34.8 MWNameplate
Generators
5 operatingEIA-860M, August 2026
Operating since
March 1987First generator online
Operator
Chickadee 3-G Purchaser LLCEIA operator ID 7375
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Jefferson County, TX29.9728, −94.2142
EIA plant ID
54321EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Chickadee G-3 produces

Free · EIA-923

Net generation, 2025

259 GWh

259,225 MWh, final

Capacity factor, 2025

85.0%

2024: 90.2%

January to July 2026

119 GWh

Provisional

Range, 2015 to 2025

208.1–275.6

GWh a year. Low 2020, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001246,701Not reported12 of 12
2002255,805Not reported12 of 12
2003Not reportedNot reported0 of 12
2004249,961Not reported12 of 12
2005246,146Not reported12 of 12
2006267,573Not reported12 of 12
2007271,601Not reported12 of 12
2008244,751Not reported12 of 12
2009214,406Not reported12 of 12
2010339,640111.4%12 of 12
2011258,56784.8%12 of 12
2012234,88776.8%12 of 12
2013238,39478.2%12 of 12
2014232,60876.3%12 of 12
2015234,22876.8%12 of 12
2016230,52575.4%12 of 12
2017209,91468.9%12 of 12
2018221,99672.8%12 of 12
2019227,95174.8%12 of 12
2020208,06668.1%12 of 12
2021269,04888.3%12 of 12
2022263,96894.3%11 of 12
2023259,07685.0%12 of 12
2024275,64990.2%12 of 12
2025259,22585.0%12 of 12
2026 (provisional, partial year)119,47867.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
2N80Natural Gas Fired Combustion Turbine5.0August 1999
3N80Natural Gas Steam Turbine14.8March 1987
N802Natural Gas Fired Combustion Turbine5.0August 1999
N803Natural Gas Fired Combustion Turbine5.0October 1999
N804Natural Gas Fired Combustion Turbine5.0October 1999

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Chickadee 3-G Purchaser LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Chickadee G-3 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Chickadee G-3

Questions about Chickadee G-3

How much power does Chickadee G-3 produce?

Chickadee G-3 reported 259,225 MWh (259 GWh) of net generation in 2025, a 85.0% capacity factor on 34.8 MW of nameplate capacity. From January to July 2026 it reported 119 GWh, which is provisional.

Where is Chickadee G-3?

Chickadee G-3 is in Jefferson County, Texas, at 29.9728, −94.2142. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Chickadee G-3?

EIA-860M for August 2026 lists Chickadee 3-G Purchaser LLC as the operator (EIA operator ID 7375). The operator is not always the owner.

When did Chickadee G-3 start operating?

Its first generator began operating in March 1987, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page