Turnkey Landfill Gas Recovery
Landfill gas power plant in Strafford County, New Hampshire. 9.2 MW of nameplate capacity across 6 generators, operated by WM Renewable Energy LLC.
Also known as EIA plant 54663
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 9.2 MWNameplate
- Generators
- 6 operatingEIA-860M, August 2026
- Operating since
- February 1992First generator online
- Operator
- WM Renewable Energy LLCEIA operator ID 54842
- Grid
- ISO-NEBalancing authority ISNE
- Price nodes
- 1 ISONE nodeResource nodes with prices
- Location
- Strafford County, NH43.2416, −70.9664
- EIA plant ID
- 54663EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Turnkey Landfill Gas Recovery produces
Free · EIA-923Net generation, 2025
38.5 GWh
38,501 MWh, final
Capacity factor, 2025
47.8%
2024: 54.6%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
26.3–44.8
GWh a year. Low 2016, high 2023
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | 71,136 | Not reported | 12 of 12 |
| 2002 | 66,388 | Not reported | 12 of 12 |
| 2003 | 69,756 | Not reported | 12 of 12 |
| 2004 | 63,956 | Not reported | 12 of 12 |
| 2005 | 68,522 | Not reported | 12 of 12 |
| 2006 | 65,172 | Not reported | 12 of 12 |
| 2007 | 65,141 | Not reported | 12 of 12 |
| 2008 | 66,479 | Not reported | 12 of 12 |
| 2009 | 63,187 | Not reported | 12 of 12 |
| 2010 | 37,271 | 46.2% | 12 of 12 |
| 2011 | 29,779 | 37.0% | 12 of 12 |
| 2012 | 30,553 | 37.8% | 12 of 12 |
| 2013 | 27,758 | 34.4% | 12 of 12 |
| 2014 | 29,484 | 36.6% | 12 of 12 |
| 2015 | 27,150 | 33.7% | 12 of 12 |
| 2016 | 26,310 | 32.6% | 12 of 12 |
| 2017 | 27,181 | 33.7% | 12 of 12 |
| 2018 | 28,317 | 35.1% | 12 of 12 |
| 2019 | 33,621 | 41.7% | 12 of 12 |
| 2020 | 32,794 | 40.6% | 12 of 12 |
| 2021 | 38,577 | 47.9% | 12 of 12 |
| 2022 | 43,339 | 53.8% | 12 of 12 |
| 2023 | 44,802 | 55.6% | 12 of 12 |
| 2024 | 44,163 | 54.6% | 12 of 12 |
| 2025 | 38,501 | 47.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · ISONEEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| GEN1 | Landfill Gas | 0.8 | February 1992 |
| GEN2 | Landfill Gas | 0.8 | February 1992 |
| GEN3 | Landfill Gas | 0.8 | February 1992 |
| GEN4 | Landfill Gas | 0.8 | September 1993 |
| GEN5 | Landfill Gas | 3.0 | December 1997 |
| GEN6 | Landfill Gas | 3.0 | December 1997 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists WM Renewable Energy LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Turnkey Landfill Gas Recovery and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Turnkey Landfill Gas Recovery
More plants operated by WM Renewable Energy LLC
Questions about Turnkey Landfill Gas Recovery
How much power does Turnkey Landfill Gas Recovery produce?
Turnkey Landfill Gas Recovery reported 38,501 MWh (38.5 GWh) of net generation in 2025, a 47.8% capacity factor on 9.2 MW of nameplate capacity.
Where is Turnkey Landfill Gas Recovery?
Turnkey Landfill Gas Recovery is in Strafford County, New Hampshire, at 43.2416, −70.9664. It is in the ISO New England Inc. balancing area (ISNE).
Who operates Turnkey Landfill Gas Recovery?
EIA-860M for August 2026 lists WM Renewable Energy LLC as the operator (EIA operator ID 54842). The operator is not always the owner.
When did Turnkey Landfill Gas Recovery start operating?
Its first generator began operating in February 1992, according to EIA-860M.
Does InfraMap have power prices for Turnkey Landfill Gas Recovery?
Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Turnkey Landfill Gas Recovery, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page