HydroOperatingMISO

Kimberly Mill

Hydro power plant in Outagamie County, Wisconsin. 2.1 MW of nameplate capacity across 3 generators, operated by City of Kaukauna (WI).

Also known as Kimberly Hydro Plant · EIA plant 54885

Analyst: free account, 1 question a day.

Combined Locks Energy…Rapide CrocheNew BadgerKimberly Mill2 km
Open in the map
6 plants within 5.5 km, from EIA coordinates.

Key facts

Capacity
2.1 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
January 1926First generator online
Operator
City of Kaukauna (WI)EIA operator ID 10056
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Outagamie County, WI44.2769, −88.3344
EIA plant ID
54885EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Kimberly Mill produces

Free · EIA-923

Net generation, 2025

13.3 GWh

13,276 MWh, final

Capacity factor, 2025

72.2%

2024: 74.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

12.3–14.2

GWh a year. Low 2023, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001107,371Not reported12 of 12
2002132,732Not reported12 of 12
200347,081Not reported4 of 12
2004146,522Not reported12 of 12
2005149,069Not reported12 of 12
2006136,754Not reported12 of 12
2007147,464Not reported12 of 12
200890,920Not reported12 of 12
20090Not reported12 of 12
20100Not reported12 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
201312,99270.6%12 of 12
201413,95275.8%12 of 12
201512,58168.4%12 of 12
201614,20577.0%12 of 12
201713,40072.8%12 of 12
201813,17471.6%12 of 12
201912,43667.6%12 of 12
202013,45372.9%12 of 12
202113,95775.9%12 of 12
202213,15071.5%12 of 12
202312,27366.7%12 of 12
202413,69974.3%12 of 12
202513,27672.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1HConventional Hydroelectric0.7January 1926
2HConventional Hydroelectric0.7January 1927
3HConventional Hydroelectric0.7January 1927

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Kaukauna (WI) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Kimberly Mill and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Kimberly Mill

More plants operated by City of Kaukauna (WI)

Questions about Kimberly Mill

How much power does Kimberly Mill produce?

Kimberly Mill reported 13,276 MWh (13.3 GWh) of net generation in 2025, a 72.2% capacity factor on 2.1 MW of nameplate capacity.

Where is Kimberly Mill?

Kimberly Mill is in Outagamie County, Wisconsin, at 44.2769, −88.3344. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Kimberly Mill?

EIA-860M for August 2026 lists City of Kaukauna (WI) as the operator (EIA operator ID 10056). The operator is not always the owner.

When did Kimberly Mill start operating?

Its first generator began operating in January 1926, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page