Wood biomassOperatingBPAT

Sierra Pacific Aberdeen

Wood biomass power plant in Grays Harbor County, Washington. 18 MW of nameplate capacity across 1 generator, operated by Sierra Pacific Industries.

Also known as Sierra Pacific Aberdeen Power Plant · EIA plant 55882

Analyst: free account, 1 question a day.

Grays Harbor Energy F…Coastal Energy ProjectWynoocheeSierra Pacific Aberdeen25 km
Open in the map
3 plants within 48 km, from EIA coordinates.

Key facts

Capacity
18 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
March 2003First generator online
Operator
Sierra Pacific IndustriesEIA operator ID 17164
Grid
BPATBalancing authority BPAT
Price nodes
None linkedNo verified ISO node
Location
Grays Harbor County, WA46.9728, −123.7739
EIA plant ID
55882EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Sierra Pacific Aberdeen produces

Free · EIA-923

Net generation, 2025

91.4 GWh

91,420 MWh, final

Capacity factor, 2025

58.0%

2024: 81.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

91.4–128.4

GWh a year. Low 2025, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
200363,701Not reported12 of 12
2004121,163Not reported12 of 12
2005125,658Not reported12 of 12
2006121,634Not reported12 of 12
2007111,324Not reported12 of 12
2008117,008Not reported12 of 12
2009119,566Not reported12 of 12
2010122,21577.5%12 of 12
2011124,77879.1%12 of 12
2012117,92274.6%12 of 12
2013119,30375.7%12 of 12
2014122,13177.5%12 of 12
2015124,17278.7%12 of 12
2016118,69675.1%12 of 12
2017122,39277.6%12 of 12
2018122,36677.6%12 of 12
2019117,83174.7%12 of 12
2020124,60478.8%12 of 12
2021123,12278.1%12 of 12
2022118,58575.2%12 of 12
2023105,15766.7%12 of 12
2024128,35081.2%12 of 12
202591,42058.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Wood/Wood Waste Biomass18.0March 2003

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Sierra Pacific Industries as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Sierra Pacific Aberdeen and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Sierra Pacific Aberdeen

More plants operated by Sierra Pacific Industries

Questions about Sierra Pacific Aberdeen

How much power does Sierra Pacific Aberdeen produce?

Sierra Pacific Aberdeen reported 91,420 MWh (91.4 GWh) of net generation in 2025, a 58.0% capacity factor on 18 MW of nameplate capacity.

Where is Sierra Pacific Aberdeen?

Sierra Pacific Aberdeen is in Grays Harbor County, Washington, at 46.9728, −123.7739. It is in the Bonneville Power Administration balancing area (BPAT).

Who operates Sierra Pacific Aberdeen?

EIA-860M for August 2026 lists Sierra Pacific Industries as the operator (EIA operator ID 17164). The operator is not always the owner.

When did Sierra Pacific Aberdeen start operating?

Its first generator began operating in March 2003, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page