Sweetwater Wind 2 LLC
Wind power plant in Nolan County, Texas. 98.8 MW of nameplate capacity across 1 generator, operated by Leeward Asset Management, LLC.
Also known as Sweetwater Wind 2 · Sweetwater Phase II · EIA plant 56212
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 98.8 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- February 2005First generator online
- Operator
- Leeward Asset Management, LLCEIA operator ID 50123
- Grid
- ERCOTBalancing authority ERCO
- Price nodes
- 1 ERCOT nodeResource nodes with prices
- Location
- Nolan County, TX32.3472, −100.3703
- EIA plant ID
- 56212EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Sweetwater Wind 2 produces
Free · EIA-923Net generation, 2025
352 GWh
351,691 MWh, final
Capacity factor, 2025
40.6%
2024: 39.2%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
256.6–429.5
GWh a year. Low 2017, high 2023
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | 262,659 | Not reported | 12 of 12 |
| 2006 | 313,075 | Not reported | 12 of 12 |
| 2007 | 279,581 | Not reported | 12 of 12 |
| 2008 | 309,123 | Not reported | 12 of 12 |
| 2009 | 299,164 | Not reported | 12 of 12 |
| 2010 | 290,015 | 36.2% | 12 of 12 |
| 2011 | 313,783 | 39.1% | 12 of 12 |
| 2012 | 301,114 | 37.5% | 12 of 12 |
| 2013 | 307,886 | 38.4% | 12 of 12 |
| 2014 | 323,607 | 40.4% | 12 of 12 |
| 2015 | 283,044 | 35.3% | 12 of 12 |
| 2016 | 297,092 | 37.0% | 12 of 12 |
| 2017 | 256,576 | Not reported | 12 of 12 |
| 2018 | 366,172 | 42.3% | 12 of 12 |
| 2019 | 364,634 | 42.1% | 12 of 12 |
| 2020 | 343,906 | 39.6% | 12 of 12 |
| 2021 | 369,510 | 42.7% | 12 of 12 |
| 2022 | 379,922 | 43.9% | 12 of 12 |
| 2023 | 429,530 | 49.6% | 12 of 12 |
| 2024 | 340,592 | 39.2% | 12 of 12 |
| 2025 | 351,691 | 40.6% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · ERCOTEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| SW2 | Onshore Wind Turbine | 98.8 | February 2005 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Leeward Asset Management, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Sweetwater Wind 2 LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Sweetwater Wind 2
More plants operated by Leeward Asset Management, LLC
Questions about Sweetwater Wind 2
How much power does Sweetwater Wind 2 LLC produce?
Sweetwater Wind 2 LLC reported 351,691 MWh (352 GWh) of net generation in 2025, a 40.6% capacity factor on 98.8 MW of nameplate capacity.
Where is Sweetwater Wind 2 LLC?
Sweetwater Wind 2 LLC is in Nolan County, Texas, at 32.3472, −100.3703. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).
Who operates Sweetwater Wind 2 LLC?
EIA-860M for August 2026 lists Leeward Asset Management, LLC as the operator (EIA operator ID 50123). The operator is not always the owner.
When did Sweetwater Wind 2 LLC start operating?
Its first generator began operating in February 2005, according to EIA-860M.
Does InfraMap have power prices for Sweetwater Wind 2 LLC?
Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Sweetwater Wind 2 LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page