WindOperatingERCOT

Horse Hollow Wind Energy Center

Wind power plant in Taylor County, Texas. 735.5 MW of nameplate capacity across 3 generators, operated by FPL Energy Horse Hollow LLC.

Also known as Horse Hollow III · Horse Hollow II · Horse Hollow Expansion · EIA plant 56291

Analyst: free account, 1 question a day.

Buffalo Gap 3 Wind FarmCallahan Divide Wind…Holstein 1 Solar FarmTurkey Track Wind Ene…Horse Hollow10 km
Open in the map
6 plants within 20 km, from EIA coordinates.

Key facts

Capacity
735.5 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
December 2005First generator online
Operator
FPL Energy Horse Hollow LLCEIA operator ID 50063
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Taylor County, TX32.2140, −100.0571
EIA plant ID
56291EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Horse Hollow produces

Free · EIA-923

Net generation, 2025

2.42 TWh

2,421,594 MWh, final

Capacity factor, 2025

37.6%

2024: 38.0%

January to July 2026

1.37 TWh

Provisional. 6 of 7 months reported

Range, 2015 to 2025

2.0–2.5

TWh a year. Low 2015, high 2020

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005204,191Not reported12 of 12
20061,323,204Not reported12 of 12
20071,850,979Not reported12 of 12
20082,027,183Not reported12 of 12
20091,269,348Not reported12 of 12
20101,845,11428.6%12 of 12
20111,846,04528.7%12 of 12
20121,879,02829.1%12 of 12
20131,463,40422.7%12 of 12
20142,309,10035.8%12 of 12
20151,965,89530.5%12 of 12
20162,159,58333.4%12 of 12
20171,972,96430.6%12 of 12
20182,440,17237.9%12 of 12
20192,493,46338.7%12 of 12
20202,513,45738.9%12 of 12
20212,313,97335.9%12 of 12
20222,336,22036.3%12 of 12
20232,282,28735.4%12 of 12
20242,458,07138.0%12 of 12
20252,421,59437.6%12 of 12
2026 (provisional, partial year)1,368,05642.8%6 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine213.0December 2005
2Onshore Wind Turbine223.5June 2006
3Onshore Wind Turbine299.0June 2006

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists FPL Energy Horse Hollow LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Horse Hollow Wind Energy Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Horse Hollow

Questions about Horse Hollow

How much power does Horse Hollow Wind Energy Center produce?

Horse Hollow Wind Energy Center reported 2,421,594 MWh (2.42 TWh) of net generation in 2025, a 37.6% capacity factor on 735.5 MW of nameplate capacity. From January to July 2026 it reported 1.37 TWh, which is provisional.

Where is Horse Hollow Wind Energy Center?

Horse Hollow Wind Energy Center is in Taylor County, Texas, at 32.2140, −100.0571. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Horse Hollow Wind Energy Center?

EIA-860M for August 2026 lists FPL Energy Horse Hollow LLC as the operator (EIA operator ID 50063). The operator is not always the owner.

When did Horse Hollow Wind Energy Center start operating?

Its first generator began operating in December 2005, according to EIA-860M.

Does InfraMap have power prices for Horse Hollow Wind Energy Center?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Horse Hollow Wind Energy Center, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page