WindOperatingMISO

Adams Wind Farm

Wind power plant in Mower County, Minnesota. 23.3 MW of nameplate capacity across 2 generators, operated by Justin McNeilus.

Also known as G. McNeilus Wind Farm · EIA plant 56307

Analyst: free account, 1 question a day.

Louise SolarPioneer Prairie Wind FarmMower County Wind Energy CenterPrairie Star Wind FarmGrand Meadow (PV)Turtle Creek Wind Farm LLCAdams Wind Farm10 km
Open in the map
6 plants within 17 km, from EIA coordinates.

Key facts

Capacity
23.3 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
September 2003First generator online
Operator
Justin McNeilusEIA operator ID 6985
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Mower County, MN43.5548, −92.7241
EIA plant ID
56307EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Adams Wind Farm produces

Free · EIA-923

Net generation, 2025

2.98 GWh

2,980 MWh, final

Capacity factor, 2025

1.5%

2024: 9.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

3.0–59.2

GWh a year. Low 2025, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
200448,352Not reported12 of 12
200556,952Not reported12 of 12
200665,593Not reported12 of 12
200769,469Not reported12 of 12
200865,998Not reported12 of 12
200960,575Not reported12 of 12
201056,08326.7%12 of 12
201159,63928.4%12 of 12
201261,70629.3%12 of 12
201359,686Not reported12 of 12
201460,76728.9%12 of 12
201559,20728.2%12 of 12
201657,25927.2%12 of 12
201755,15926.2%12 of 12
201847,27022.5%12 of 12
201945,609Not reported12 of 12
202047,88923.4%12 of 12
202140,77620.0%12 of 12
202241,79720.5%12 of 12
202329,32014.4%12 of 12
202420,2459.9%12 of 12
20252,9801.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine13.5September 2003
2Onshore Wind Turbine9.8July 2004

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Justin McNeilus as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Adams Wind Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Adams Wind Farm

More plants operated by Justin McNeilus

Questions about Adams Wind Farm

How much power does Adams Wind Farm produce?

Adams Wind Farm reported 2,980 MWh (2.98 GWh) of net generation in 2025, a 1.5% capacity factor on 23.3 MW of nameplate capacity.

Where is Adams Wind Farm?

Adams Wind Farm is in Mower County, Minnesota, at 43.5548, −92.7241. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Adams Wind Farm?

EIA-860M for August 2026 lists Justin McNeilus as the operator (EIA operator ID 6985). The operator is not always the owner.

When did Adams Wind Farm start operating?

Its first generator began operating in September 2003, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page