Adams Wind Farm
Wind power plant in Mower County, Minnesota. 23.3 MW of nameplate capacity across 2 generators, operated by Justin McNeilus.
Also known as G. McNeilus Wind Farm · EIA plant 56307
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 23.3 MWNameplate
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- September 2003First generator online
- Operator
- Justin McNeilusEIA operator ID 6985
- Grid
- MISOBalancing authority MISO
- Price nodes
- None linkedNo verified ISO node
- Location
- Mower County, MN43.5548, −92.7241
- EIA plant ID
- 56307EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Adams Wind Farm produces
Free · EIA-923Net generation, 2025
2.98 GWh
2,980 MWh, final
Capacity factor, 2025
1.5%
2024: 9.9%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
3.0–59.2
GWh a year. Low 2025, high 2015
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | 48,352 | Not reported | 12 of 12 |
| 2005 | 56,952 | Not reported | 12 of 12 |
| 2006 | 65,593 | Not reported | 12 of 12 |
| 2007 | 69,469 | Not reported | 12 of 12 |
| 2008 | 65,998 | Not reported | 12 of 12 |
| 2009 | 60,575 | Not reported | 12 of 12 |
| 2010 | 56,083 | 26.7% | 12 of 12 |
| 2011 | 59,639 | 28.4% | 12 of 12 |
| 2012 | 61,706 | 29.3% | 12 of 12 |
| 2013 | 59,686 | Not reported | 12 of 12 |
| 2014 | 60,767 | 28.9% | 12 of 12 |
| 2015 | 59,207 | 28.2% | 12 of 12 |
| 2016 | 57,259 | 27.2% | 12 of 12 |
| 2017 | 55,159 | 26.2% | 12 of 12 |
| 2018 | 47,270 | 22.5% | 12 of 12 |
| 2019 | 45,609 | Not reported | 12 of 12 |
| 2020 | 47,889 | 23.4% | 12 of 12 |
| 2021 | 40,776 | 20.0% | 12 of 12 |
| 2022 | 41,797 | 20.5% | 12 of 12 |
| 2023 | 29,320 | 14.4% | 12 of 12 |
| 2024 | 20,245 | 9.9% | 12 of 12 |
| 2025 | 2,980 | 1.5% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Onshore Wind Turbine | 13.5 | September 2003 |
| 2 | Onshore Wind Turbine | 9.8 | July 2004 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Justin McNeilus as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Adams Wind Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Adams Wind Farm
More plants operated by Justin McNeilus
Questions about Adams Wind Farm
How much power does Adams Wind Farm produce?
Adams Wind Farm reported 2,980 MWh (2.98 GWh) of net generation in 2025, a 1.5% capacity factor on 23.3 MW of nameplate capacity.
Where is Adams Wind Farm?
Adams Wind Farm is in Mower County, Minnesota, at 43.5548, −92.7241. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Adams Wind Farm?
EIA-860M for August 2026 lists Justin McNeilus as the operator (EIA operator ID 6985). The operator is not always the owner.
When did Adams Wind Farm start operating?
Its first generator began operating in September 2003, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page