Landfill gasOperatingNYISO

Colonie LFGTE Facility

Landfill gas power plant in Albany County, New York. 6.4 MW of nameplate capacity across 4 generators, operated by Innovative Energy Systems Inc.

Also known as EIA plant 56324

Analyst: free account, 1 question a day.

School StreetFourth Branch Hydroel…New York State Dam HydroGoldman Sachs Carports SolarTown of HalfmoonColonie LFGTE Facility2 km
Open in the map
6 plants within 5.5 km, from EIA coordinates.

Key facts

Capacity
6.4 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
February 2006First generator online
Operator
Innovative Energy Systems IncEIA operator ID 50158
Grid
NYISOBalancing authority NYIS
Price nodes
1 NYISO nodeResource nodes with prices
Location
Albany County, NY42.8033, −73.7267
EIA plant ID
56324EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Colonie LFGTE Facility produces

Free · EIA-923

Net generation, 2025

39.7 GWh

39,745 MWh, final

Capacity factor, 2025

70.9%

2024: 72.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

25.9–40.9

GWh a year. Low 2019, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
200624,869Not reported12 of 12
200733,513Not reported12 of 12
200836,781Not reported12 of 12
200936,392Not reported12 of 12
201035,02583.3%12 of 12
201130,72373.1%12 of 12
201228,85668.4%12 of 12
201331,46074.8%12 of 12
201437,01988.0%12 of 12
201535,05483.4%12 of 12
201634,902Not reported12 of 12
201735,36063.1%12 of 12
201834,52461.6%12 of 12
201925,90146.2%12 of 12
202029,70152.8%12 of 12
202134,49061.5%12 of 12
202237,01066.0%12 of 12
202334,63761.8%12 of 12
202440,89272.7%12 of 12
202539,74570.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · NYISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Landfill Gas1.6February 2006
GEN2Landfill Gas1.6February 2006
GEN3Landfill Gas1.6February 2006
GEN4Landfill Gas1.6June 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Innovative Energy Systems Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Colonie LFGTE Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Colonie LFGTE Facility

More plants operated by Innovative Energy Systems Inc

Questions about Colonie LFGTE Facility

How much power does Colonie LFGTE Facility produce?

Colonie LFGTE Facility reported 39,745 MWh (39.7 GWh) of net generation in 2025, a 70.9% capacity factor on 6.4 MW of nameplate capacity.

Where is Colonie LFGTE Facility?

Colonie LFGTE Facility is in Albany County, New York, at 42.8033, −73.7267. It is in the New York Independent System Operator balancing area (NYIS).

Who operates Colonie LFGTE Facility?

EIA-860M for August 2026 lists Innovative Energy Systems Inc as the operator (EIA operator ID 50158). The operator is not always the owner.

When did Colonie LFGTE Facility start operating?

Its first generator began operating in February 2006, according to EIA-860M.

Does InfraMap have power prices for Colonie LFGTE Facility?

Yes. InfraMap has NYISO day-ahead and real-time prices at 1 price node linked to Colonie LFGTE Facility, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • NYISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page