Electric Avenue Facility
Oil power plant in Culpeper County, Virginia. 6.9 MW of nameplate capacity across 4 generators, operated by Town of Culpeper- (VA).
Also known as EIA plant 56367
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 6.9 MWNameplate
- Generators
- 4 operatingEIA-860M, August 2026
- Operating since
- February 1997First generator online
- Operator
- Town of Culpeper- (VA)EIA operator ID 4619
- Grid
- PJMBalancing authority PJM
- Price nodes
- None linkedNo verified ISO node
- Location
- Culpeper County, VA38.2800, −77.5900
- EIA plant ID
- 56367EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Electric Avenue Facility produces
Free · EIA-923Net generation, 2025
659 MWh
659 MWh, final
Capacity factor, 2025
1.1%
2024: 0.7%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
29.0–659.0
MWh a year. Low 2017, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | 730 | Not reported | 12 of 12 |
| 2008 | 413 | Not reported | 12 of 12 |
| 2009 | 336 | Not reported | 12 of 12 |
| 2010 | 131 | 0.3% | 12 of 12 |
| 2011 | 63 | 0.1% | 12 of 12 |
| 2012 | 139 | 0.3% | 12 of 12 |
| 2013 | 86 | 0.2% | 12 of 12 |
| 2014 | 91 | 0.2% | 12 of 12 |
| 2015 | 144 | 0.3% | 12 of 12 |
| 2016 | 50 | 0.1% | 12 of 12 |
| 2017 | 29 | 0.0% | 12 of 12 |
| 2018 | 120 | 0.2% | 12 of 12 |
| 2019 | 292 | 0.5% | 12 of 12 |
| 2020 | 555 | 0.9% | 12 of 12 |
| 2021 | 475 | 0.8% | 12 of 12 |
| 2022 | 647 | 1.1% | 12 of 12 |
| 2023 | 480 | 0.8% | 12 of 12 |
| 2024 | 443 | 0.7% | 12 of 12 |
| 2025 | 659 | 1.1% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Petroleum Liquids | 1.8 | December 2004 |
| 2 | Petroleum Liquids | 1.8 | December 2004 |
| 3 | Petroleum Liquids | 1.8 | December 2004 |
| 4 | Petroleum Liquids | 1.5 | February 1997 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Town of Culpeper- (VA) as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Electric Avenue Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Electric Avenue Facility
Questions about Electric Avenue Facility
How much power does Electric Avenue Facility produce?
Electric Avenue Facility reported 659 MWh (659 MWh) of net generation in 2025, a 1.1% capacity factor on 6.9 MW of nameplate capacity.
Where is Electric Avenue Facility?
Electric Avenue Facility is in Culpeper County, Virginia, at 38.2800, −77.5900. It is in the PJM Interconnection, LLC balancing area (PJM).
Who operates Electric Avenue Facility?
EIA-860M for August 2026 lists Town of Culpeper- (VA) as the operator (EIA operator ID 4619). The operator is not always the owner.
When did Electric Avenue Facility start operating?
Its first generator began operating in February 1997, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page