Forest Creek Wind Farm LLC
Wind power plant in Glasscock County, Texas. 124.2 MW of nameplate capacity across 1 generator, operated by RWE Clean Energy.
Also known as Forest Creek Wind Farm · Forest Creek Wind Project · EIA plant 56394
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 124.2 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- December 2006First generator online
- Operator
- RWE Clean EnergyEIA operator ID 67192
- Grid
- ERCOTBalancing authority ERCO
- Price nodes
- 1 ERCOT nodeResource nodes with prices
- Location
- Glasscock County, TX32.0390, −101.2200
- EIA plant ID
- 56394EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Forest Creek Wind Farm produces
Free · EIA-923Net generation, 2025
128 GWh
128,394 MWh, final
Capacity factor, 2025
11.8%
2024: 16.6%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
128.4–386.5
GWh a year. Low 2025, high 2017
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | 5,001 | Not reported | 1 of 12 |
| 2007 | 371,870 | Not reported | 12 of 12 |
| 2008 | 427,333 | Not reported | 12 of 12 |
| 2009 | 360,733 | Not reported | 12 of 12 |
| 2010 | 387,622 | 35.6% | 12 of 12 |
| 2011 | 425,385 | 39.1% | 12 of 12 |
| 2012 | 417,897 | 38.3% | 12 of 12 |
| 2013 | 395,405 | 36.3% | 12 of 12 |
| 2014 | 425,923 | 39.1% | 12 of 12 |
| 2015 | 363,553 | 33.4% | 12 of 12 |
| 2016 | 308,508 | 28.3% | 12 of 12 |
| 2017 | 386,462 | 35.5% | 12 of 12 |
| 2018 | 367,110 | 33.7% | 12 of 12 |
| 2019 | 335,782 | 30.9% | 12 of 12 |
| 2020 | 312,715 | 28.7% | 12 of 12 |
| 2021 | 271,400 | 24.9% | 12 of 12 |
| 2022 | 239,438 | 22.0% | 12 of 12 |
| 2023 | 225,448 | 20.7% | 12 of 12 |
| 2024 | 180,942 | 16.6% | 12 of 12 |
| 2025 | 128,394 | 11.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · ERCOTEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Onshore Wind Turbine | 124.2 | December 2006 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists RWE Clean Energy as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Forest Creek Wind Farm LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Forest Creek Wind Farm
More plants operated by RWE Clean Energy
Questions about Forest Creek Wind Farm
How much power does Forest Creek Wind Farm LLC produce?
Forest Creek Wind Farm LLC reported 128,394 MWh (128 GWh) of net generation in 2025, a 11.8% capacity factor on 124.2 MW of nameplate capacity.
Where is Forest Creek Wind Farm LLC?
Forest Creek Wind Farm LLC is in Glasscock County, Texas, at 32.0390, −101.2200. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).
Who operates Forest Creek Wind Farm LLC?
EIA-860M for August 2026 lists RWE Clean Energy as the operator (EIA operator ID 67192). The operator is not always the owner.
When did Forest Creek Wind Farm LLC start operating?
Its first generator began operating in December 2006, according to EIA-860M.
Does InfraMap have power prices for Forest Creek Wind Farm LLC?
Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Forest Creek Wind Farm LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page