Spanish Fork Wind Park 2 LLC
Wind power plant in Utah County, Utah. 18.9 MW of nameplate capacity across 1 generator, operated by Spanish Fork Wind Park 2, LLC.
Also known as Spanish Fork Wind Park 2 · EIA plant 56751
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 18.9 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- July 2008First generator online
- Operator
- Spanish Fork Wind Park 2, LLCEIA operator ID 64661
- Grid
- PACEBalancing authority PACE
- Price nodes
- None linkedNo verified ISO node
- Location
- Utah County, UT40.0714, −111.5822
- EIA plant ID
- 56751EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Spanish Fork Wind Park 2 produces
Free · EIA-923Net generation, 2025
42.2 GWh
42,217 MWh, final
Capacity factor, 2025
25.5%
2024: 27.0%
January to July 2026
20.0 GWh
Provisional. 6 of 7 months reported
Range, 2015 to 2025
42.1–49.1
GWh a year. Low 2022, high 2019
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | 23,900 | Not reported | 12 of 12 |
| 2009 | 46,415 | Not reported | 12 of 12 |
| 2010 | 46,929 | 28.3% | 12 of 12 |
| 2011 | 47,379 | 28.6% | 12 of 12 |
| 2012 | 39,991 | 24.1% | 12 of 12 |
| 2013 | 46,031 | 27.8% | 12 of 12 |
| 2014 | 44,786 | 27.1% | 12 of 12 |
| 2015 | 45,915 | 27.7% | 12 of 12 |
| 2016 | 48,248 | 29.1% | 12 of 12 |
| 2017 | 46,460 | 28.1% | 12 of 12 |
| 2018 | 44,398 | 26.8% | 12 of 12 |
| 2019 | 49,052 | 29.6% | 12 of 12 |
| 2020 | 46,312 | 27.9% | 12 of 12 |
| 2021 | 45,624 | 27.6% | 12 of 12 |
| 2022 | 42,121 | 25.4% | 12 of 12 |
| 2023 | 45,040 | 27.2% | 12 of 12 |
| 2024 | 44,775 | 27.0% | 12 of 12 |
| 2025 | 42,217 | 25.5% | 12 of 12 |
| 2026 (provisional, partial year) | 20,026 | 24.4% | 6 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Onshore Wind Turbine | 18.9 | July 2008 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Spanish Fork Wind Park 2, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Spanish Fork Wind Park 2 LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Spanish Fork Wind Park 2
Questions about Spanish Fork Wind Park 2
How much power does Spanish Fork Wind Park 2 LLC produce?
Spanish Fork Wind Park 2 LLC reported 42,217 MWh (42.2 GWh) of net generation in 2025, a 25.5% capacity factor on 18.9 MW of nameplate capacity. From January to July 2026 it reported 20.0 GWh, which is provisional.
Where is Spanish Fork Wind Park 2 LLC?
Spanish Fork Wind Park 2 LLC is in Utah County, Utah, at 40.0714, −111.5822. It is in the PacifiCorp - East balancing area (PACE).
Who operates Spanish Fork Wind Park 2 LLC?
EIA-860M for August 2026 lists Spanish Fork Wind Park 2, LLC as the operator (EIA operator ID 64661). The operator is not always the owner.
When did Spanish Fork Wind Park 2 LLC start operating?
Its first generator began operating in July 2008, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page