Bent Tree Wind Farm Phase 1

Wind power plant in Freeborn County, Minnesota. 201.3 MW of nameplate capacity across 1 generator, operated by Wisconsin Power & Light Co.

Also known as Bent Tree Wind Farm · Bent Tree · EIA plant 57198

Analyst: free account, 1 question a day.

Bancroft (MN)USS Solar Way LLC CSGUSS All In Solar LLC CSGGoose Lake MN DPC-GMREG Juhl Glenville Wind, LLCBolduan CSGBent Tree Wind Farm Phase 110 km
Open in the map
6 plants within 20 km, from EIA coordinates.

Key facts

Capacity
201.3 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 2011First generator online
Operator
Wisconsin Power & Light CoEIA operator ID 20856
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Freeborn County, MN43.7246, −93.4504
EIA plant ID
57198EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Bent Tree Wind Farm Phase 1 produces

Free · EIA-923

Net generation, 2025

334 GWh

334,066 MWh, final

Capacity factor, 2025

18.9%

2024: 19.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

309.6–594.8

GWh a year. Low 2021, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011405,835Not reported11 of 12
2012430,66824.4%12 of 12
2013554,61131.5%12 of 12
2014591,03533.5%12 of 12
2015594,77133.7%12 of 12
2016574,69032.5%12 of 12
2017566,26932.1%12 of 12
2018507,56428.8%12 of 12
2019511,47929.0%12 of 12
2020520,37029.4%12 of 12
2021309,56117.6%12 of 12
2022453,04025.7%12 of 12
2023341,63519.4%12 of 12
2024342,99519.4%12 of 12
2025334,06618.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine201.3February 2011

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Wisconsin Power & Light Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Bent Tree Wind Farm Phase 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Bent Tree Wind Farm Phase 1

More plants operated by Wisconsin Power & Light Co

Questions about Bent Tree Wind Farm Phase 1

How much power does Bent Tree Wind Farm Phase 1 produce?

Bent Tree Wind Farm Phase 1 reported 334,066 MWh (334 GWh) of net generation in 2025, a 18.9% capacity factor on 201.3 MW of nameplate capacity.

Where is Bent Tree Wind Farm Phase 1?

Bent Tree Wind Farm Phase 1 is in Freeborn County, Minnesota, at 43.7246, −93.4504. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Bent Tree Wind Farm Phase 1?

EIA-860M for August 2026 lists Wisconsin Power & Light Co as the operator (EIA operator ID 20856). The operator is not always the owner.

When did Bent Tree Wind Farm Phase 1 start operating?

Its first generator began operating in February 2011, according to EIA-860M.

Does InfraMap have power prices for Bent Tree Wind Farm Phase 1?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Bent Tree Wind Farm Phase 1, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page