North Carolina Solar Bethea I
Solar power plant in Scotland County, North Carolina. 2 MW of nameplate capacity across 1 generator, operated by USF Surry, LLC.
Also known as EIA plant 58531
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 2 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- February 2013First generator online
- Operator
- USF Surry, LLCEIA operator ID 66042
- Grid
- CPLEBalancing authority CPLE
- Price nodes
- None linkedNo verified ISO node
- Location
- Scotland County, NC34.7047, −79.5258
- EIA plant ID
- 58531EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power North Carolina Solar Bethea I produces
Free · EIA-923Net generation, 2025
2.53 GWh
2,528 MWh, final
Capacity factor, 2025
14.4%
2024: 17.6%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
2.5–3.7
GWh a year. Low 2025, high 2017
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | 1,822 | Not reported | 11 of 12 |
| 2014 | 3,354 | 38.3% | 12 of 12 |
| 2015 | 3,640 | 41.6% | 12 of 12 |
| 2016 | 2,983 | 34.0% | 12 of 12 |
| 2017 | 3,662 | 41.8% | 12 of 12 |
| 2018 | 3,043 | 34.7% | 12 of 12 |
| 2019 | 3,310 | 37.8% | 12 of 12 |
| 2020 | 3,112 | 35.4% | 12 of 12 |
| 2021 | 3,347 | Not reported | 12 of 12 |
| 2022 | 3,303 | 18.9% | 12 of 12 |
| 2023 | 3,074 | 17.5% | 12 of 12 |
| 2024 | 3,089 | 17.6% | 12 of 12 |
| 2025 | 2,528 | 14.4% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| P22A | Solar Photovoltaic | 2.0 | February 2013 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists USF Surry, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query North Carolina Solar Bethea I and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near North Carolina Solar Bethea I
More plants operated by USF Surry, LLC
Questions about North Carolina Solar Bethea I
How much power does North Carolina Solar Bethea I produce?
North Carolina Solar Bethea I reported 2,528 MWh (2.53 GWh) of net generation in 2025, a 14.4% capacity factor on 2 MW of nameplate capacity.
Where is North Carolina Solar Bethea I?
North Carolina Solar Bethea I is in Scotland County, North Carolina, at 34.7047, −79.5258. It is in the Duke Energy Progress East balancing area (CPLE).
Who operates North Carolina Solar Bethea I?
EIA-860M for August 2026 lists USF Surry, LLC as the operator (EIA operator ID 66042). The operator is not always the owner.
When did North Carolina Solar Bethea I start operating?
Its first generator began operating in February 2013, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page