Landfill gasOperatingPSEI

LRI LFGTE Facility

Landfill gas power plant in Pierce County, Washington. 4.5 MW of nameplate capacity across 3 generators, operated by Frontier Operation Services.

Also known as EIA plant 58688

Analyst: free account, 1 question a day.

FredericksonFrederickson Power LPLaGrandeAlderYelmLRI LFGTE Facility10 km
Open in the map
6 plants within 26 km, from EIA coordinates.

Key facts

Capacity
4.5 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
November 2013First generator online
Operator
Frontier Operation ServicesEIA operator ID 63199
Grid
PSEIBalancing authority PSEI
Price nodes
None linkedNo verified ISO node
Location
Pierce County, WA46.9756, −122.2906
EIA plant ID
58688EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power LRI LFGTE Facility produces

Free · EIA-923

Net generation, 2025

33.2 GWh

33,180 MWh, final

Capacity factor, 2025

84.2%

2024: 81.1%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

27.2–36.7

GWh a year. Low 2021, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
20131,564Not reported2 of 12
201436,67793.0%12 of 12
201534,08386.5%12 of 12
201636,72492.9%12 of 12
201736,22991.9%12 of 12
201833,93186.1%12 of 12
201931,47379.8%12 of 12
202031,17978.9%12 of 12
202127,19669.0%12 of 12
202231,85080.8%12 of 12
202333,60585.2%12 of 12
202432,05381.1%12 of 12
202533,18084.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ALandfill Gas1.5November 2013
BLandfill Gas1.5November 2013
CLandfill Gas1.5November 2013

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Frontier Operation Services as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query LRI LFGTE Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near LRI LFGTE Facility

More plants operated by Frontier Operation Services

Questions about LRI LFGTE Facility

How much power does LRI LFGTE Facility produce?

LRI LFGTE Facility reported 33,180 MWh (33.2 GWh) of net generation in 2025, a 84.2% capacity factor on 4.5 MW of nameplate capacity.

Where is LRI LFGTE Facility?

LRI LFGTE Facility is in Pierce County, Washington, at 46.9756, −122.2906. It is in the Puget Sound Energy balancing area (PSEI).

Who operates LRI LFGTE Facility?

EIA-860M for August 2026 lists Frontier Operation Services as the operator (EIA operator ID 63199). The operator is not always the owner.

When did LRI LFGTE Facility start operating?

Its first generator began operating in November 2013, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page