SolarOperatingISO-NE

Katama Farm

Solar power plant in Dukes County, Massachusetts. 1 MW of nameplate capacity across 1 generator, operated by Clean Focus Yield, LLC.

Also known as EIA plant 59079

Analyst: free account, 1 question a day.

Tisbury Landfill SolarBlacksmith Road Solar 1Notus Wind 1Katama Farm10 km
Open in the map
6 plants within 29 km, from EIA coordinates.

Key facts

Capacity
1 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 2014First generator online
Operator
Clean Focus Yield, LLCEIA operator ID 65305
Grid
ISO-NEBalancing authority ISNE
Price nodes
None linkedNo verified ISO node
Location
Dukes County, MA41.3611, −70.5169
EIA plant ID
59079EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Katama Farm produces

Free · EIA-923

Net generation, 2025

1.64 GWh

1,641 MWh, final

Capacity factor, 2025

18.7%

2024: 16.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.9–1.7

GWh a year. Low 2017, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014793Not reported7 of 12
20151,58118.0%12 of 12
20161,66118.9%12 of 12
201790010.3%12 of 12
20181,22614.0%12 of 12
20191,45116.6%12 of 12
20201,37615.7%12 of 12
20211,42516.3%12 of 12
20221,43716.4%12 of 12
20231,60018.3%12 of 12
20241,47816.8%12 of 12
20251,64118.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
KAT1Solar Photovoltaic1.0June 2014

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Clean Focus Yield, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Katama Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Katama Farm

More plants operated by Clean Focus Yield, LLC

Questions about Katama Farm

How much power does Katama Farm produce?

Katama Farm reported 1,641 MWh (1.64 GWh) of net generation in 2025, a 18.7% capacity factor on 1 MW of nameplate capacity.

Where is Katama Farm?

Katama Farm is in Dukes County, Massachusetts, at 41.3611, −70.5169. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Katama Farm?

EIA-860M for August 2026 lists Clean Focus Yield, LLC as the operator (EIA operator ID 65305). The operator is not always the owner.

When did Katama Farm start operating?

Its first generator began operating in June 2014, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page