SolarOperatingISO-NE

Easton Landfill

Solar power plant in Bristol County, Massachusetts. 1.6 MW of nameplate capacity across 1 generator, operated by CleanCapital Holdings.

Also known as EIA plant 59134

Analyst: free account, 1 question a day.

Ajax Solar, LLC (MA)West Bridgewater AB CSGStone Hill Solar CSGNorton Landfill SolarEaston Landfill2 km
Open in the map
6 plants within 7.4 km, from EIA coordinates.

Key facts

Capacity
1.6 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
October 2013First generator online
Operator
CleanCapital HoldingsEIA operator ID 65164
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Bristol County, MA42.0103, −71.0922
EIA plant ID
59134EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Easton Landfill produces

Free · EIA-923

Net generation, 2025

2.54 GWh

2,539 MWh, final

Capacity factor, 2025

18.1%

2024: 17.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

2.2–2.7

GWh a year. Low 2023, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013309Not reported3 of 12
20142,47514.9%12 of 12
20152,52515.2%12 of 12
20162,65415.9%12 of 12
20172,45414.7%12 of 12
20182,34014.1%12 of 12
20192,33814.0%12 of 12
20202,52615.1%12 of 12
20212,439Not reported12 of 12
20222,49417.8%12 of 12
20232,22915.9%12 of 12
20242,48117.7%12 of 12
20252,53918.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
57449Solar Photovoltaic1.6October 2013

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists CleanCapital Holdings as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Easton Landfill and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Easton Landfill

More plants operated by CleanCapital Holdings

Questions about Easton Landfill

How much power does Easton Landfill produce?

Easton Landfill reported 2,539 MWh (2.54 GWh) of net generation in 2025, a 18.1% capacity factor on 1.6 MW of nameplate capacity.

Where is Easton Landfill?

Easton Landfill is in Bristol County, Massachusetts, at 42.0103, −71.0922. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Easton Landfill?

EIA-860M for August 2026 lists CleanCapital Holdings as the operator (EIA operator ID 65164). The operator is not always the owner.

When did Easton Landfill start operating?

Its first generator began operating in October 2013, according to EIA-860M.

Does InfraMap have power prices for Easton Landfill?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Easton Landfill, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page