Key facts

Capacity
50.4 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 2016First generator online
Operator
Clearway Renewable Operation & Maintenance LLCEIA operator ID 64629
Grid
PACEBalancing authority PACE
Price nodes
None linkedNo verified ISO node
Location
Iron County, UT37.7989, −113.3220
EIA plant ID
59945EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Granite Mountain Solar West produces

Free · EIA-923

Net generation, 2025

125 GWh

125,158 MWh, final

Capacity factor, 2025

28.3%

2024: 29.0%

January to July 2026

75.0 GWh

Provisional

Range, 2017 to 2025

110.7–131.3

GWh a year. Low 2022, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
201625,727Not reported5 of 12
2017127,97129.0%12 of 12
2018123,56728.0%12 of 12
2019125,44028.4%12 of 12
2020131,28529.7%12 of 12
2021125,09328.3%12 of 12
2022110,65825.1%12 of 12
2023120,87327.4%12 of 12
2024128,18829.0%12 of 12
2025125,15828.3%12 of 12
2026 (provisional, partial year)75,01529.3%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GMSWSolar Photovoltaic50.4September 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Clearway Renewable Operation & Maintenance LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Granite Mountain Solar West, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Granite Mountain Solar West

More plants operated by Clearway Renewable Operation & Maintenance LLC

Questions about Granite Mountain Solar West

How much power does Granite Mountain Solar West, LLC produce?

Granite Mountain Solar West, LLC reported 125,158 MWh (125 GWh) of net generation in 2025, a 28.3% capacity factor on 50.4 MW of nameplate capacity. From January to July 2026 it reported 75.0 GWh, which is provisional.

Where is Granite Mountain Solar West, LLC?

Granite Mountain Solar West, LLC is in Iron County, Utah, at 37.7989, −113.3220. It is in the PacifiCorp - East balancing area (PACE).

Who operates Granite Mountain Solar West, LLC?

EIA-860M for August 2026 lists Clearway Renewable Operation & Maintenance LLC as the operator (EIA operator ID 64629). The operator is not always the owner.

When did Granite Mountain Solar West, LLC start operating?

Its first generator began operating in September 2016, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page