Five Forks Solar
Solar power plant in Warren County, North Carolina. 20 MW of nameplate capacity across 1 generator, operated by Five Forks Solar.
Also known as EIA plant 59951
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 20 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- December 2019First generator online
- Operator
- Five Forks SolarEIA operator ID 61857
- Grid
- PJMBalancing authority PJM
- Price nodes
- None linkedNo verified ISO node
- Location
- Warren County, NC36.5155, −78.0337
- EIA plant ID
- 59951EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Five Forks Solar produces
Free · EIA-923Net generation, 2025
32.7 GWh
32,687 MWh, final
Capacity factor, 2025
18.7%
2024: 15.3%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2020 to 2025
26.8–41.5
GWh a year. Low 2024, high 2021
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | 278 | Not reported | 1 of 12 |
| 2020 | 39,754 | 22.6% | 12 of 12 |
| 2021 | 41,463 | 23.7% | 12 of 12 |
| 2022 | 38,599 | 22.0% | 12 of 12 |
| 2023 | 35,815 | 20.4% | 12 of 12 |
| 2024 | 26,847 | 15.3% | 12 of 12 |
| 2025 | 32,687 | 18.7% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 5FRK | Solar Photovoltaic | 20.0 | December 2019 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Five Forks Solar as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Five Forks Solar and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Five Forks Solar
Questions about Five Forks Solar
How much power does Five Forks Solar produce?
Five Forks Solar reported 32,687 MWh (32.7 GWh) of net generation in 2025, a 18.7% capacity factor on 20 MW of nameplate capacity.
Where is Five Forks Solar?
Five Forks Solar is in Warren County, North Carolina, at 36.5155, −78.0337. It is in the PJM Interconnection, LLC balancing area (PJM).
Who operates Five Forks Solar?
EIA-860M for August 2026 lists Five Forks Solar as the operator (EIA operator ID 61857). The operator is not always the owner.
When did Five Forks Solar start operating?
Its first generator began operating in December 2019, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page