Town of Chestertown- Chestertown WWTP
Solar power plant in Kent County, Maryland. 1 MW of nameplate capacity across 1 generator, operated by Tesla Inc..
Also known as Town of Chestertown-Chestertown WWTP · EIA plant 60096
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 1 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- December 2015First generator online
- Operator
- Tesla Inc.EIA operator ID 57313
- Grid
- PJMBalancing authority PJM
- Price nodes
- None linkedNo verified ISO node
- Location
- Kent County, MD39.1995, −76.0767
- EIA plant ID
- 60096EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Town of Chestertown- Chestertown WWTP produces
Free · EIA-923Net generation, 2025
1.65 GWh
1,653 MWh, final
Capacity factor, 2025
18.9%
2024: 19.4%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2016 to 2025
1.6–1.9
GWh a year. Low 2023, high 2021
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | 24 | Not reported | 1 of 12 |
| 2016 | 1,815 | 20.7% | 12 of 12 |
| 2017 | 1,798 | 20.5% | 12 of 12 |
| 2018 | 1,673 | 19.1% | 12 of 12 |
| 2019 | 1,790 | 20.4% | 12 of 12 |
| 2020 | 1,591 | 18.1% | 12 of 12 |
| 2021 | 1,856 | 21.2% | 12 of 12 |
| 2022 | 1,585 | 18.1% | 12 of 12 |
| 2023 | 1,576 | 18.0% | 12 of 12 |
| 2024 | 1,701 | 19.4% | 12 of 12 |
| 2025 | 1,653 | 18.9% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| PV1 | Solar Photovoltaic | 1.0 | December 2015 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Tesla Inc. as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Town of Chestertown- Chestertown WWTP and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Town of Chestertown- Chestertown WWTP
More plants operated by Tesla Inc.
Questions about Town of Chestertown- Chestertown WWTP
How much power does Town of Chestertown- Chestertown WWTP produce?
Town of Chestertown- Chestertown WWTP reported 1,653 MWh (1.65 GWh) of net generation in 2025, a 18.9% capacity factor on 1 MW of nameplate capacity.
Where is Town of Chestertown- Chestertown WWTP?
Town of Chestertown- Chestertown WWTP is in Kent County, Maryland, at 39.1995, −76.0767. It is in the PJM Interconnection, LLC balancing area (PJM).
Who operates Town of Chestertown- Chestertown WWTP?
EIA-860M for August 2026 lists Tesla Inc. as the operator (EIA operator ID 57313). The operator is not always the owner.
When did Town of Chestertown- Chestertown WWTP start operating?
Its first generator began operating in December 2015, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page