SolarOperatingNEVP

Tesla Reno GigaFactory

Solar power plant in Storey County, Nevada. 6.7 MW of nameplate capacity across 6 generators, operated by Tesla Inc..

Also known as EIA plant 64098

Analyst: free account, 1 question a day.

Chukar Battery Energy Storage SystemTracyTurquoise Nevada, LLCTurquoise Liberty SolarTesla Reno GigaFactory5 km
Open in the map
5 plants within 8.9 km, from EIA coordinates.

Key facts

Capacity
6.7 MWNameplate
Generators
6 operatingEIA-860M, August 2026
Operating since
June 2019First generator online
Operator
Tesla Inc.EIA operator ID 57313
Grid
NEVPBalancing authority NEVP
Price nodes
None linkedNo verified ISO node
Location
Storey County, NV39.5395, −119.4392
EIA plant ID
64098EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Tesla Reno GigaFactory produces

Free · EIA-923

Net generation, 2025

5.06 GWh

5,062 MWh, final

Capacity factor, 2025

8.6%

2024: 14.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2020 to 2025

1.4–11.1

GWh a year. Low 2020, high 2023

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
20201,41117.8%12 of 12
20211,409Not reported2 of 12
20229,444Not reported12 of 12
202311,11218.9%12 of 12
20248,73514.8%12 of 12
20255,0628.6%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Solar Photovoltaic0.4July 2019
2Solar Photovoltaic0.5June 2019
5Solar Photovoltaic0.9November 2021
RASolar Photovoltaic1.1March 2022
RBSolar Photovoltaic1.8April 2022
RCSolar Photovoltaic2.0July 2022

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Tesla Inc. as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Tesla Reno GigaFactory and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Tesla Reno GigaFactory

More plants operated by Tesla Inc.

Questions about Tesla Reno GigaFactory

How much power does Tesla Reno GigaFactory produce?

Tesla Reno GigaFactory reported 5,062 MWh (5.06 GWh) of net generation in 2025, a 8.6% capacity factor on 6.7 MW of nameplate capacity.

Where is Tesla Reno GigaFactory?

Tesla Reno GigaFactory is in Storey County, Nevada, at 39.5395, −119.4392. It is in the Nevada Power Company balancing area (NEVP).

Who operates Tesla Reno GigaFactory?

EIA-860M for August 2026 lists Tesla Inc. as the operator (EIA operator ID 57313). The operator is not always the owner.

When did Tesla Reno GigaFactory start operating?

Its first generator began operating in June 2019, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page