Natural gasOperatingMISO

Greenwood (MI)

Natural gas power plant in St Clair County, Michigan. 1,071.3 MW of nameplate capacity across 4 generators, operated by DTE Electric Company.

Also known as Greenwood Energy Center Industrial Park · EIA plant 6035

Analyst: free account, 1 question a day.

Blue Water Renewables IncCargill SaltPine Tree Acres WM LFGTEPine Tree AcresGreenwood (MI)20 km
Open in the map
6 plants within 38 km, from EIA coordinates.

Key facts

Capacity
1,071.3 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
July 1979First generator online
Operator
DTE Electric CompanyEIA operator ID 5109
Grid
MISOBalancing authority MISO
Price nodes
4 MISO nodesResource nodes with prices
Location
St Clair County, MI43.1056, −82.6964
EIA plant ID
6035EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Greenwood (MI) produces

Free · EIA-923

Net generation, 2025

1.25 TWh

1,249,697 MWh, final

Capacity factor, 2025

13.3%

2024: 15.5%

January to July 2026

1.01 TWh

Provisional

Range, 2015 to 2025

0.2–1.5

TWh a year. Low 2015, high 2024

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20001,115,973Not reported12 of 12
2001919,256Not reported12 of 12
20021,170,155Not reported12 of 12
2003625,067Not reported12 of 12
2004455,280Not reported12 of 12
2005757,414Not reported12 of 12
2006307,174Not reported12 of 12
2007422,553Not reported12 of 12
2008257,050Not reported12 of 12
2009177,219Not reported12 of 12
2010536,1555.7%12 of 12
2011373,6964.0%12 of 12
20123,5700.4%1 of 12
2013369,3803.9%12 of 12
2014223,9943.6%8 of 12
2015202,0942.2%12 of 12
2016529,5355.6%12 of 12
2017524,9705.6%12 of 12
2018806,7978.6%12 of 12
2019947,51110.1%12 of 12
2020954,18110.1%12 of 12
2021795,7958.5%12 of 12
2022454,5494.8%12 of 12
20231,025,49710.9%12 of 12
20241,455,44115.5%12 of 12
20251,249,69713.3%12 of 12
2026 (provisional, partial year)1,009,27818.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

CO₂, 2025

860,435

US short tons. 2024: 837,326

SO₂, 2025

4

US short tons

NOx, 2025

719

US short tons

CO₂ per MWh, calculated

0.69 t

About 1,377 lb per MWh

4 of 4 EPA units reported CO₂ in 2025 (1, CTG111, CTG112, CTG121), matched to EIA plant 6035 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

78,762

million gallons

Consumption, 2024

0

million gallons

Source

Municipal

Surface, Fresh. Recirculating with cooling pond

Watershed stress

Low · 0.200

USGS SUI, HUC12 Silver Creek

12 of 12 cooling months report withdrawal. SUI of the HUC12 containing the plant. Cooling-pond plants report water circulated through the pond as withdrawal, so withdrawal is far above consumption. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Natural Gas Steam Turbine815.4July 1979
11-1Natural Gas Fired Combustion Turbine85.3September 1999
11-2Natural Gas Fired Combustion Turbine85.3September 1999
11-3Natural Gas Fired Combustion Turbine85.3September 1999

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists DTE Electric Company as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Greenwood (MI) and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Greenwood (MI)

More plants operated by DTE Electric Company

Questions about Greenwood (MI)

How much power does Greenwood (MI) produce?

Greenwood (MI) reported 1,249,697 MWh (1.25 TWh) of net generation in 2025, a 13.3% capacity factor on 1,071.3 MW of nameplate capacity. From January to July 2026 it reported 1.01 TWh, which is provisional.

Where is Greenwood (MI)?

Greenwood (MI) is in St Clair County, Michigan, at 43.1056, −82.6964. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Greenwood (MI)?

EIA-860M for August 2026 lists DTE Electric Company as the operator (EIA operator ID 5109). The operator is not always the owner.

When did Greenwood (MI) start operating?

Its first generator began operating in July 1979, according to EIA-860M.

Does InfraMap have power prices for Greenwood (MI)?

Yes. InfraMap has MISO day-ahead and real-time prices at 4 price nodes linked to Greenwood (MI), with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page