SolarOperatingDUK

Wortham Solar Farm

Solar power plant in Vance County, North Carolina. 5 MW of nameplate capacity across 1 generator, operated by Cypress Creek Renewables.

Also known as EIA plant 60361

Analyst: free account, 1 question a day.

Spring Valley Farm 2, LLCVicksburg SolarStainback Solar FarmMartin Creek Farm LLCKelly Solar, LLCBearPond Solar Center LLCWortham Solar Farm5 km
Open in the map
6 plants within 8.5 km, from EIA coordinates.

Key facts

Capacity
5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 2016First generator online
Operator
Cypress Creek RenewablesEIA operator ID 61060
Grid
DUKBalancing authority DUK
Price nodes
None linkedNo verified ISO node
Location
Vance County, NC36.3525, −78.3763
EIA plant ID
60361EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Wortham Solar Farm produces

Free · EIA-923

Net generation, 2025

8.84 GWh

8,839 MWh, final

Capacity factor, 2025

20.2%

2024: 20.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2017 to 2025

8.4–9.1

GWh a year. Low 2020, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
20162,196Not reported4 of 12
20178,97920.5%12 of 12
20188,78320.1%12 of 12
20199,11620.8%12 of 12
20208,41319.2%12 of 12
20218,84820.2%12 of 12
20229,03120.6%12 of 12
20238,90620.3%12 of 12
20249,04220.6%12 of 12
20258,83920.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
INV1Solar Photovoltaic5.0September 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Cypress Creek Renewables as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Wortham Solar Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Wortham Solar Farm

More plants operated by Cypress Creek Renewables

Questions about Wortham Solar Farm

How much power does Wortham Solar Farm produce?

Wortham Solar Farm reported 8,839 MWh (8.84 GWh) of net generation in 2025, a 20.2% capacity factor on 5 MW of nameplate capacity.

Where is Wortham Solar Farm?

Wortham Solar Farm is in Vance County, North Carolina, at 36.3525, −78.3763. It is in the Duke Energy Carolinas balancing area (DUK).

Who operates Wortham Solar Farm?

EIA-860M for August 2026 lists Cypress Creek Renewables as the operator (EIA operator ID 61060). The operator is not always the owner.

When did Wortham Solar Farm start operating?

Its first generator began operating in September 2016, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page