Key facts

Capacity
200 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
November 2016First generator online
Operator
Javelina Wind Energy II, LLCEIA operator ID 60384
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Webb County, TX27.4400, −98.9100
EIA plant ID
60645EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Javelina Wind Energy II produces

Free · EIA-923

Net generation, 2025

762 GWh

761,596 MWh, final

Capacity factor, 2025

43.5%

2024: 39.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2017 to 2025

688.7–798.2

GWh a year. Low 2024, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
201669,982Not reported2 of 12
2017772,35844.1%12 of 12
2018798,21445.6%12 of 12
2019756,14443.2%12 of 12
2020773,69644.0%12 of 12
2021764,95843.7%12 of 12
2022769,42643.9%12 of 12
2023727,91841.5%12 of 12
2024688,66639.2%12 of 12
2025761,59643.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
WJ21Onshore Wind Turbine200.0November 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Javelina Wind Energy II, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Javelina Wind Energy II, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Javelina Wind Energy II

Questions about Javelina Wind Energy II

How much power does Javelina Wind Energy II, LLC produce?

Javelina Wind Energy II, LLC reported 761,596 MWh (762 GWh) of net generation in 2025, a 43.5% capacity factor on 200 MW of nameplate capacity.

Where is Javelina Wind Energy II, LLC?

Javelina Wind Energy II, LLC is in Webb County, Texas, at 27.4400, −98.9100. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Javelina Wind Energy II, LLC?

EIA-860M for August 2026 lists Javelina Wind Energy II, LLC as the operator (EIA operator ID 60384). The operator is not always the owner.

When did Javelina Wind Energy II, LLC start operating?

Its first generator began operating in November 2016, according to EIA-860M.

Does InfraMap have power prices for Javelina Wind Energy II, LLC?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Javelina Wind Energy II, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page