Boulder Solar II, LLC
Solar power plant in Clark County, Nevada. 50 MW of nameplate capacity across 1 generator, operated by Invenergy Services LLC.
Also known as Boulder Solar II · EIA plant 60885
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 50 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- January 2017First generator online
- Operator
- Invenergy Services LLCEIA operator ID 49893
- Grid
- NEVPBalancing authority NEVP
- Price nodes
- None linkedNo verified ISO node
- Location
- Clark County, NV35.8500, −114.9440
- EIA plant ID
- 60885EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Boulder Solar II produces
Free · EIA-923Net generation, 2025
111 GWh
110,547 MWh, final
Capacity factor, 2025
25.2%
2024: 27.9%
January to July 2026
60.4 GWh
Provisional
Range, 2017 to 2025
110.5–136.7
GWh a year. Low 2025, high 2020
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | 133,711 | Not reported | 12 of 12 |
| 2018 | 135,238 | 30.9% | 12 of 12 |
| 2019 | 131,190 | 30.0% | 12 of 12 |
| 2020 | 136,743 | 31.1% | 12 of 12 |
| 2021 | 129,330 | 29.5% | 12 of 12 |
| 2022 | 130,085 | 29.7% | 12 of 12 |
| 2023 | 126,011 | 28.8% | 12 of 12 |
| 2024 | 122,696 | 27.9% | 12 of 12 |
| 2025 | 110,547 | 25.2% | 12 of 12 |
| 2026 (provisional, partial year) | 60,408 | 23.7% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| BSII | Solar Photovoltaic | 50.0 | January 2017 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Invenergy Services LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Boulder Solar II, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Boulder Solar II
More plants operated by Invenergy Services LLC
Questions about Boulder Solar II
How much power does Boulder Solar II, LLC produce?
Boulder Solar II, LLC reported 110,547 MWh (111 GWh) of net generation in 2025, a 25.2% capacity factor on 50 MW of nameplate capacity. From January to July 2026 it reported 60.4 GWh, which is provisional.
Where is Boulder Solar II, LLC?
Boulder Solar II, LLC is in Clark County, Nevada, at 35.8500, −114.9440. It is in the Nevada Power Company balancing area (NEVP).
Who operates Boulder Solar II, LLC?
EIA-860M for August 2026 lists Invenergy Services LLC as the operator (EIA operator ID 49893). The operator is not always the owner.
When did Boulder Solar II, LLC start operating?
Its first generator began operating in January 2017, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page