SolarBattery storageOperating

AES Lawai Solar Hybrid

Solar and battery storage project in Kauai County, Hawaii. 40 MW of nameplate capacity across 2 generators, operated by AES Distributed Energy.

Also known as EIA plant 61068

This project groups AES Lawai Solar Hybrid (EIA 61068). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

KRS II Koloa SolarKalaheo HydroBiomass to Energy Facility, KauaiPort Allen Solar5 km
Open in the map
5 plants within 9.6 km, from EIA coordinates.

Key facts

Capacity
40 MWSolar 20.0 · Battery storage 20.0
Generators
2 operatingEIA-860M, August 2026
Operating since
December 2018First generator online
Operator
AES Distributed EnergyEIA operator ID 61012
Grid
Not reported
Price nodes
None linkedNo verified ISO node
Location
Kauai County, HI21.9082, −159.4920
EIA plant ID
61068EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power AES Lawai Solar Hybrid produces

Free · EIA-923

Net generation, 2025

40.2 GWh

40,226 MWh, final

Capacity factor, 2025

23.4%

2024: 20.8%

January to July 2026

23.3 GWh

Provisional

Range, 2019 to 2025

33.2–40.2

GWh a year. Low 2022, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
20180Not reported1 of 12
201937,50121.4%12 of 12
202038,88822.2%12 of 12
202138,99322.3%12 of 12
202233,18319.0%12 of 12
202335,49420.6%12 of 12
202436,09820.8%12 of 12
202540,22623.4%12 of 12
2026 (provisional, partial year)23,25223.2%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LAWA1Solar Photovoltaic20.0December 2018
LAWA2Batteries20.0December 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists AES Distributed Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query AES Lawai Solar Hybrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near AES Lawai Solar Hybrid

More plants operated by AES Distributed Energy

Questions about AES Lawai Solar Hybrid

How much power does AES Lawai Solar Hybrid produce?

AES Lawai Solar Hybrid reported 40,226 MWh (40.2 GWh) of net generation in 2025, a 23.4% capacity factor on 40 MW of nameplate capacity. From January to July 2026 it reported 23.3 GWh, which is provisional.

Where is AES Lawai Solar Hybrid?

AES Lawai Solar Hybrid is in Kauai County, Hawaii, at 21.9082, −159.4920.

Who operates AES Lawai Solar Hybrid?

EIA-860M for August 2026 lists AES Distributed Energy as the operator (EIA operator ID 61012). The operator is not always the owner.

Is AES Lawai Solar Hybrid a solar or a battery storage plant?

Both. Solar capacity totals 20 MW and battery storage capacity totals 20 MW.

When did AES Lawai Solar Hybrid start operating?

Its first generator began operating in December 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page