Pine River Wind Park
Wind power plant in Isabella County, Michigan. 161.3 MW of nameplate capacity across 1 generator, operated by DTE Electric Company.
Also known as Pine River · EIA plant 61106
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 161.3 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- March 2019First generator online
- Operator
- DTE Electric CompanyEIA operator ID 5109
- Grid
- MISOBalancing authority MISO
- Price nodes
- 1 MISO nodeResource nodes with prices
- Location
- Isabella County, MI43.5243, −84.6968
- EIA plant ID
- 61106EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Pine River Wind Park produces
Free · EIA-923Net generation, 2025
381 GWh
380,627 MWh, final
Capacity factor, 2025
26.9%
2024: 23.8%
January to July 2026
239 GWh
Provisional
Range, 2020 to 2025
336.7–419.7
GWh a year. Low 2024, high 2022
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | 256,835 | Not reported | 10 of 12 |
| 2020 | 415,654 | 29.3% | 12 of 12 |
| 2021 | 381,645 | 27.0% | 12 of 12 |
| 2022 | 419,671 | 29.7% | 12 of 12 |
| 2023 | 345,176 | 24.4% | 12 of 12 |
| 2024 | 336,678 | 23.8% | 12 of 12 |
| 2025 | 380,627 | 26.9% | 12 of 12 |
| 2026 (provisional, partial year) | 239,030 | 29.1% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · MISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Onshore Wind Turbine | 161.3 | March 2019 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists DTE Electric Company as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Pine River Wind Park and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Pine River Wind Park
More plants operated by DTE Electric Company
Questions about Pine River Wind Park
How much power does Pine River Wind Park produce?
Pine River Wind Park reported 380,627 MWh (381 GWh) of net generation in 2025, a 26.9% capacity factor on 161.3 MW of nameplate capacity. From January to July 2026 it reported 239 GWh, which is provisional.
Where is Pine River Wind Park?
Pine River Wind Park is in Isabella County, Michigan, at 43.5243, −84.6968. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Pine River Wind Park?
EIA-860M for August 2026 lists DTE Electric Company as the operator (EIA operator ID 5109). The operator is not always the owner.
When did Pine River Wind Park start operating?
Its first generator began operating in March 2019, according to EIA-860M.
Does InfraMap have power prices for Pine River Wind Park?
Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Pine River Wind Park, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page