WindOperatingMISO

August Wind Farm

Wind power plant in Taylor County, Iowa. 1.8 MW of nameplate capacity across 1 generator, operated by August Wind Energy, LLC.

Also known as August Wind Energy LLC · EIA plant 61644

Analyst: free account, 1 question a day.

Adams WindContrail Wind FarmPOET Biorefining LLC - CorningCreston School Customer Hosted SolarCreston Solar (50 MW)August Wind Farm20 km
Open in the map
6 plants within 36 km, from EIA coordinates.

Key facts

Capacity
1.8 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 2017First generator online
Operator
August Wind Energy, LLCEIA operator ID 61254
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Taylor County, IA40.7649, −94.4756
EIA plant ID
61644EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power August Wind Farm produces

Free · EIA-923

Net generation, 2025

5.54 GWh

5,544 MWh, final

Capacity factor, 2025

35.2%

2024: 40.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2018 to 2025

5.5–8.2

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
20176,285Not reported11 of 12
20187,02144.5%12 of 12
20197,27146.1%12 of 12
20206,96744.1%12 of 12
20215,68336.0%12 of 12
20228,17551.8%12 of 12
20236,75942.9%12 of 12
20246,46340.9%12 of 12
20255,54435.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
AUGOnshore Wind Turbine1.8February 2017

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists August Wind Energy, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query August Wind Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near August Wind Farm

Questions about August Wind Farm

How much power does August Wind Farm produce?

August Wind Farm reported 5,544 MWh (5.54 GWh) of net generation in 2025, a 35.2% capacity factor on 1.8 MW of nameplate capacity.

Where is August Wind Farm?

August Wind Farm is in Taylor County, Iowa, at 40.7649, −94.4756. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates August Wind Farm?

EIA-860M for August 2026 lists August Wind Energy, LLC as the operator (EIA operator ID 61254). The operator is not always the owner.

When did August Wind Farm start operating?

Its first generator began operating in February 2017, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page