Persimmon Creek Wind Farm 1, LLC
Wind power plant in Woodward County, Oklahoma. 198.6 MW of nameplate capacity across 1 generator, operated by Evergy Kansas Central, Inc.
Also known as Persimmon Creek Wind Farm 1 · Persimmon Creek I · EIA plant 61876
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 198.6 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- September 2018First generator online
- Operator
- Evergy Kansas Central, IncEIA operator ID 22500
- Grid
- SPPBalancing authority SWPP
- Price nodes
- 1 SPP nodeResource nodes with prices
- Location
- Woodward County, OK36.1743, −99.3492
- EIA plant ID
- 61876EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Persimmon Creek Wind Farm 1 produces
Free · EIA-923Net generation, 2025
826 GWh
825,826 MWh, final
Capacity factor, 2025
47.5%
2024: 50.2%
January to July 2026
511 GWh
Provisional
Range, 2019 to 2025
820.1–925.8
GWh a year. Low 2021, high 2019
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | 279,097 | Not reported | 4 of 12 |
| 2019 | 925,805 | 53.2% | 12 of 12 |
| 2020 | 905,174 | 51.9% | 12 of 12 |
| 2021 | 820,084 | 47.1% | 12 of 12 |
| 2022 | 832,909 | 47.9% | 12 of 12 |
| 2023 | 827,708 | 47.6% | 12 of 12 |
| 2024 | 876,145 | 50.2% | 12 of 12 |
| 2025 | 825,826 | 47.5% | 12 of 12 |
| 2026 (provisional, partial year) | 511,156 | 50.6% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · SPPEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| PCWF1 | Onshore Wind Turbine | 198.6 | September 2018 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Evergy Kansas Central, Inc as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Persimmon Creek Wind Farm 1, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Persimmon Creek Wind Farm 1
More plants operated by Evergy Kansas Central, Inc
Questions about Persimmon Creek Wind Farm 1
How much power does Persimmon Creek Wind Farm 1, LLC produce?
Persimmon Creek Wind Farm 1, LLC reported 825,826 MWh (826 GWh) of net generation in 2025, a 47.5% capacity factor on 198.6 MW of nameplate capacity. From January to July 2026 it reported 511 GWh, which is provisional.
Where is Persimmon Creek Wind Farm 1, LLC?
Persimmon Creek Wind Farm 1, LLC is in Woodward County, Oklahoma, at 36.1743, −99.3492. It is in the Southwest Power Pool balancing area (SWPP).
Who operates Persimmon Creek Wind Farm 1, LLC?
EIA-860M for August 2026 lists Evergy Kansas Central, Inc as the operator (EIA operator ID 22500). The operator is not always the owner.
When did Persimmon Creek Wind Farm 1, LLC start operating?
Its first generator began operating in September 2018, according to EIA-860M.
Does InfraMap have power prices for Persimmon Creek Wind Farm 1, LLC?
Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Persimmon Creek Wind Farm 1, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page