HydroOperatingSCL

Ross

Hydro power plant in Whatcom County, Washington. 450 MW of nameplate capacity across 4 generators, operated by City of Seattle - (WA).

Also known as Ross Dam Powerhouse · EIA plant 6202

Analyst: free account, 1 question a day.

GorgeUpper BakerLower BakerNooksack HydroRoss25 km
Open in the map
6 plants within 58 km, from EIA coordinates.

Key facts

Capacity
450 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
December 1952First generator online
Operator
City of Seattle - (WA)EIA operator ID 16868
Grid
SCLBalancing authority SCL
Price nodes
4 CAISO nodesResource nodes with prices
Location
Whatcom County, WA48.7326, −121.0679
EIA plant ID
6202EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Ross produces

Free · EIA-923

Net generation, 2025

532 GWh

531,608 MWh, final

Capacity factor, 2025

13.5%

2024: 10.4%

January to July 2026

451 GWh

Provisional

Range, 2015 to 2025

410.1–822.3

GWh a year. Low 2024, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000739,062Not reported12 of 12
2001390,312Not reported12 of 12
2002834,803Not reported12 of 12
2003725,036Not reported12 of 12
2004678,712Not reported12 of 12
2005561,114Not reported12 of 12
2006638,651Not reported12 of 12
2007857,197Not reported12 of 12
2008656,306Not reported12 of 12
2009619,116Not reported12 of 12
2010645,726Not reported12 of 12
2011868,24222.0%12 of 12
2012937,81423.7%12 of 12
2013724,32718.4%12 of 12
2014794,41320.2%12 of 12
2015682,79217.3%12 of 12
2016789,494Not reported12 of 12
2017739,553Not reported12 of 12
2018688,16617.5%12 of 12
2019522,60013.3%12 of 12
2020653,93216.5%12 of 12
2021822,30720.9%12 of 12
2022747,22519.0%12 of 12
2023411,55110.4%12 of 12
2024410,10610.4%12 of 12
2025531,60813.5%12 of 12
2026 (provisional, partial year)450,59919.7%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
41Conventional Hydroelectric112.5November 1956
42Conventional Hydroelectric112.5January 1954
43Conventional Hydroelectric112.5April 1953
44Conventional Hydroelectric112.5December 1952

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Seattle - (WA) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Ross and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Ross

More plants operated by City of Seattle - (WA)

Questions about Ross

How much power does Ross produce?

Ross reported 531,608 MWh (532 GWh) of net generation in 2025, a 13.5% capacity factor on 450 MW of nameplate capacity. From January to July 2026 it reported 451 GWh, which is provisional.

Where is Ross?

Ross is in Whatcom County, Washington, at 48.7326, −121.0679. It is in the Seattle City Light balancing area (SCL).

Who operates Ross?

EIA-860M for August 2026 lists City of Seattle - (WA) as the operator (EIA operator ID 16868). The operator is not always the owner.

When did Ross start operating?

Its first generator began operating in December 1952, according to EIA-860M.

Does InfraMap have power prices for Ross?

Yes. InfraMap has CAISO day-ahead and real-time prices at 4 price nodes linked to Ross, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page