Key facts

Capacity
1.9 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
August 2018First generator online
Operator
NSTAR Electric CompanyEIA operator ID 54913
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Hampden County, MA42.1646, −72.4463
EIA plant ID
62097EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Ludlow Site 72 - Conti produces

Free · EIA-923

Net generation, 2025

2.52 GWh

2,522 MWh, final

Capacity factor, 2025

15.2%

2024: 14.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

2.0–2.6

GWh a year. Low 2019, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018516Not reported5 of 12
20192,04512.3%12 of 12
20202,62615.7%12 of 12
20212,42514.6%12 of 12
20222,62015.7%12 of 12
20232,29913.8%12 of 12
20242,48014.9%12 of 12
20252,52215.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LG390Solar Photovoltaic1.9August 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists NSTAR Electric Company as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Ludlow Site 72 - Conti and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Ludlow Site 72 - Conti

More plants operated by NSTAR Electric Company

Questions about Ludlow Site 72 - Conti

How much power does Ludlow Site 72 - Conti produce?

Ludlow Site 72 - Conti reported 2,522 MWh (2.52 GWh) of net generation in 2025, a 15.2% capacity factor on 1.9 MW of nameplate capacity.

Where is Ludlow Site 72 - Conti?

Ludlow Site 72 - Conti is in Hampden County, Massachusetts, at 42.1646, −72.4463. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Ludlow Site 72 - Conti?

EIA-860M for August 2026 lists NSTAR Electric Company as the operator (EIA operator ID 54913). The operator is not always the owner.

When did Ludlow Site 72 - Conti start operating?

Its first generator began operating in August 2018, according to EIA-860M.

Does InfraMap have power prices for Ludlow Site 72 - Conti?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Ludlow Site 72 - Conti, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page