SolarOperatingFPL

Twin Lakes

Solar power plant in Putnam County, Florida. 74.5 MW of nameplate capacity across 1 generator, operated by Florida Power & Light Co.

Also known as Twin Lakes Solar Energy Center · EIA plant 62633

Analyst: free account, 1 question a day.

Coral Farms Solar Ene…Georgia-Pacific Palatka OperationsGeorges LakeRice CreekHorizon Solar Energy CenterTwin Lakes10 km
Open in the map
6 plants within 21 km, from EIA coordinates.

Key facts

Capacity
74.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
January 2020First generator online
Operator
Florida Power & Light CoEIA operator ID 6452
Grid
FPLBalancing authority FPL
Price nodes
None linkedNo verified ISO node
Location
Putnam County, FL29.6122, −81.8445
EIA plant ID
62633EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Twin Lakes produces

Free · EIA-923

Net generation, 2025

123 GWh

122,507 MWh, final

Capacity factor, 2025

18.8%

2024: 18.8%

January to July 2026

86.1 GWh

Provisional

Range, 2020 to 2025

122.5–147.2

GWh a year. Low 2025, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020147,227Not reported12 of 12
2021144,11822.1%12 of 12
2022145,81722.3%12 of 12
2023128,65119.7%12 of 12
2024122,72418.8%12 of 12
2025122,50718.8%12 of 12
2026 (provisional, partial year)86,12622.7%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Solar Photovoltaic74.5January 2020

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Florida Power & Light Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Twin Lakes and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Twin Lakes

More plants operated by Florida Power & Light Co

Questions about Twin Lakes

How much power does Twin Lakes produce?

Twin Lakes reported 122,507 MWh (123 GWh) of net generation in 2025, a 18.8% capacity factor on 74.5 MW of nameplate capacity. From January to July 2026 it reported 86.1 GWh, which is provisional.

Where is Twin Lakes?

Twin Lakes is in Putnam County, Florida, at 29.6122, −81.8445. It is in the Florida Power & Light Company balancing area (FPL).

Who operates Twin Lakes?

EIA-860M for August 2026 lists Florida Power & Light Co as the operator (EIA operator ID 6452). The operator is not always the owner.

When did Twin Lakes start operating?

Its first generator began operating in January 2020, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page