Oil power plant in Chippewa County, Michigan. 6 MW of nameplate capacity across 2 generators, operated by Cloverland Electric Co-op.

Also known as EIA plant 6369

Analyst: free account, 1 question a day.

Pickford SolarDafterCheboyganDetour25 km
Open in the map
3 plants within 59 km, from EIA coordinates.

Key facts

Capacity
6 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
October 1973First generator online
Operator
Cloverland Electric Co-opEIA operator ID 3828
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Chippewa County, MI45.9836, −83.9079
EIA plant ID
6369EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Detour produces

Free · EIA-923

Net generation, 2025

1.84 GWh

1,841 MWh, final

Capacity factor, 2025

3.5%

2024: 2.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

−0.1–1.8

GWh a year. Low 2018, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
200128Not reported12 of 12
20020Not reported12 of 12
20031,126Not reported12 of 12
2004−230Not reported12 of 12
2005350Not reported12 of 12
200629Not reported12 of 12
2007540Not reported12 of 12
2008871Not reported12 of 12
20092,171Not reported12 of 12
20107511.4%12 of 12
20117351.4%12 of 12
20127261.4%12 of 12
20134580.9%12 of 12
20143380.6%12 of 12
201500.0%12 of 12
201600.0%12 of 12
201700.0%12 of 12
2018−92-0.2%12 of 12
20193710.7%12 of 12
20201900.4%12 of 12
20218451.6%12 of 12
20226231.2%12 of 12
20235921.1%12 of 12
20241,5122.9%12 of 12
20251,8413.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
6Petroleum Liquids3.0October 1973
7Petroleum Liquids3.0August 1976

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Cloverland Electric Co-op as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Detour and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Detour

More plants operated by Cloverland Electric Co-op

Questions about Detour

How much power does Detour produce?

Detour reported 1,841 MWh (1.84 GWh) of net generation in 2025, a 3.5% capacity factor on 6 MW of nameplate capacity.

Where is Detour?

Detour is in Chippewa County, Michigan, at 45.9836, −83.9079. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Detour?

EIA-860M for August 2026 lists Cloverland Electric Co-op as the operator (EIA operator ID 3828). The operator is not always the owner.

When did Detour start operating?

Its first generator began operating in October 1973, according to EIA-860M.

Does InfraMap have power prices for Detour?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Detour, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05