Landfill gasOperatingIPCO

Milner Butte LFGE

Landfill gas power plant in Cassia County, Idaho. 3.9 MW of nameplate capacity across 3 generators, operated by Southern Idaho Solid Waste.

Also known as EIA plant 63755

Analyst: free account, 1 question a day.

Milner Dam Wind Park LLCBurley Butte WindparkMilner HydroGolden Valley Wind Park LLCBypassS E Hazelton AMilner Butte LFGE5 km
Open in the map
6 plants within 14 km, from EIA coordinates.

Key facts

Capacity
3.9 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
October 2018First generator online
Operator
Southern Idaho Solid WasteEIA operator ID 63439
Grid
IPCOBalancing authority IPCO
Price nodes
None linkedNo verified ISO node
Location
Cassia County, ID42.4669, −114.0046
EIA plant ID
63755EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Milner Butte LFGE produces

Free · EIA-923

Net generation, 2025

26.7 GWh

26,669 MWh, final

Capacity factor, 2025

78.1%

2024: 70.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

16.3–26.7

GWh a year. Low 2019, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
201916,30371.6%12 of 12
202017,66477.3%12 of 12
202118,33480.5%12 of 12
202218,29780.3%12 of 12
202318,407Not reported12 of 12
202424,13170.4%12 of 12
202526,66978.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
E1Landfill Gas1.3June 2023
E2Landfill Gas1.3October 2018
E3Landfill Gas1.3October 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Southern Idaho Solid Waste as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Milner Butte LFGE and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Milner Butte LFGE

Questions about Milner Butte LFGE

How much power does Milner Butte LFGE produce?

Milner Butte LFGE reported 26,669 MWh (26.7 GWh) of net generation in 2025, a 78.1% capacity factor on 3.9 MW of nameplate capacity.

Where is Milner Butte LFGE?

Milner Butte LFGE is in Cassia County, Idaho, at 42.4669, −114.0046. It is in the Idaho Power Company balancing area (IPCO).

Who operates Milner Butte LFGE?

EIA-860M for August 2026 lists Southern Idaho Solid Waste as the operator (EIA operator ID 63439). The operator is not always the owner.

When did Milner Butte LFGE start operating?

Its first generator began operating in October 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page