Azure Sky Wind Project, LLC Hybrid

Wind and battery storage project in Throckmorton County, Texas. 470.2 MW of nameplate capacity across 2 generators, operated by Azure Sky Wind Project, LLC.

Also known as Azure Sky Wind Project · EIA plant 64164

This project groups Azure Sky Wind Project, LLC Hybrid (EIA 64164). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

King Creek Wind Farm 1, LLCOCI Alamo 7 LLCMillers Branch SolarHorse Creek Wind FarmAzure Sky Wind Projec…20 km
Open in the map
6 plants within 32 km, from EIA coordinates.

Key facts

Capacity
470.2 MWWind 350.2 · Battery storage 120.0
Generators
2 operatingEIA-860M, August 2026
Operating since
December 2023First generator online
Operator
Azure Sky Wind Project, LLCEIA operator ID 63784
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Throckmorton County, TX33.1691, −99.2660
EIA plant ID
64164EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Azure Sky Wind Project, LLC Hybrid produces

Free · EIA-923

Net generation, 2025

1.21 TWh

1,207,187 MWh, final

Capacity factor, 2025

39.8%

2024: Not reported

January to July 2026

771 GWh

Provisional

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023369,253Not reported4 of 12
2024842,225Not reported9 of 12
20251,207,18739.8%12 of 12
2026 (provisional, partial year)770,97943.8%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ASWBEBatteries120.0December 2023
ASWWTOnshore Wind Turbine350.2August 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Azure Sky Wind Project, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Azure Sky Wind Project, LLC Hybrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Azure Sky Wind Project, LLC Hybrid

Questions about Azure Sky Wind Project, LLC Hybrid

How much power does Azure Sky Wind Project, LLC Hybrid produce?

Azure Sky Wind Project, LLC Hybrid reported 1,207,187 MWh (1.21 TWh) of net generation in 2025, a 39.8% capacity factor on 470.2 MW of nameplate capacity. From January to July 2026 it reported 771 GWh, which is provisional.

Where is Azure Sky Wind Project, LLC Hybrid?

Azure Sky Wind Project, LLC Hybrid is in Throckmorton County, Texas, at 33.1691, −99.2660. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Azure Sky Wind Project, LLC Hybrid?

EIA-860M for August 2026 lists Azure Sky Wind Project, LLC as the operator (EIA operator ID 63784). The operator is not always the owner.

Is Azure Sky Wind Project, LLC Hybrid a wind or a battery storage plant?

Both. Wind capacity totals 350.2 MW and battery storage capacity totals 120 MW.

When did Azure Sky Wind Project, LLC Hybrid start operating?

Its first generator began operating in December 2023, according to EIA-860M.

Does InfraMap have power prices for Azure Sky Wind Project, LLC Hybrid?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Azure Sky Wind Project, LLC Hybrid, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page