Lansing Smith
Natural gas power plant in Bay County, Florida. 661.5 MW of nameplate capacity across 4 generators, operated by Florida Power & Light Co.
Also known as Lansing Smith Electric Generating Plant · EIA plant 643
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 661.5 MWNatural gas 619.7 · Oil 41.8
- Generators
- 4 operatingEIA-860M, August 2026
- Operating since
- May 1971First generator online
- Operator
- Florida Power & Light CoEIA operator ID 6452
- Grid
- FPLBalancing authority FPL
- Price nodes
- None linkedNo verified ISO node
- Location
- Bay County, FL30.2686, −85.7003
- EIA plant ID
- 643EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Lansing Smith produces
Free · EIA-923Net generation, 2025
3.75 TWh
3,747,743 MWh, final
Capacity factor, 2025
64.7%
2024: 68.2%
January to July 2026
2.09 TWh
Provisional
Range, 2017 to 2025
3.7–5.0
TWh a year. Low 2025, high 2020
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | 2,469,629 | Not reported | 12 of 12 |
| 2001 | 2,316,371 | Not reported | 12 of 12 |
| 2002 | 4,022,365 | Not reported | 12 of 12 |
| 2003 | 2,776,879 | Not reported | 9 of 12 |
| 2004 | 4,904,137 | Not reported | 12 of 12 |
| 2005 | 4,422,449 | Not reported | 12 of 12 |
| 2006 | 4,706,050 | Not reported | 12 of 12 |
| 2007 | 4,696,145 | Not reported | 12 of 12 |
| 2008 | 4,739,883 | Not reported | 12 of 12 |
| 2009 | 5,182,946 | Not reported | 12 of 12 |
| 2010 | 4,666,344 | 53.2% | 12 of 12 |
| 2011 | 5,028,403 | 57.3% | 12 of 12 |
| 2012 | 4,649,697 | 52.9% | 12 of 12 |
| 2013 | 636,110 | 43.4% | 2 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | 3,851,608 | 47.8% | 11 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | 4,139,059 | Not reported | 12 of 12 |
| 2018 | 4,032,484 | 69.6% | 12 of 12 |
| 2019 | 3,913,387 | Not reported | 12 of 12 |
| 2020 | 4,967,565 | 85.5% | 12 of 12 |
| 2021 | 4,708,398 | 81.3% | 12 of 12 |
| 2022 | 4,542,044 | 78.4% | 12 of 12 |
| 2023 | 4,184,498 | 72.2% | 12 of 12 |
| 2024 | 3,965,115 | 68.2% | 12 of 12 |
| 2025 | 3,747,743 | 64.7% | 12 of 12 |
| 2026 (provisional, partial year) | 2,094,417 | 62.2% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDCO₂, 2025
1.61M
US short tons. 2024: 1.69M
SO₂, 2025
8
US short tons
NOx, 2025
387
US short tons
CO₂ per MWh, calculated
0.43 t
About 861 lb per MWh
2 of 2 EPA units reported CO₂ in 2025 (1, 2, 4, 5, AA, AB), matched to EIA plant 643 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.
Water use
Free · EIA-923 cooling, USGSWithdrawal, 2024
1,463
million gallons
Consumption, 2024
531
million gallons
Source
North Bay
Surface, Brackish. Induced-draft tower
Watershed stress
Low · 0.205
USGS SUI, HUC12 Fannin Bayou-Frontal West Bay
12 of 12 cooling months report withdrawal. Saline, brackish or ocean intake; not tested. Blank volumes are unreported, not zero.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 3A | Natural Gas Fired Combined Cycle | 203.2 | April 2002 |
| 3B | Natural Gas Fired Combined Cycle | 203.2 | April 2002 |
| 3S | Natural Gas Fired Combined Cycle | 213.3 | April 2002 |
| CT1 | Petroleum Liquids | 41.8 | May 1971 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Florida Power & Light Co as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Lansing Smith and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Lansing Smith
More plants operated by Florida Power & Light Co
Questions about Lansing Smith
How much power does Lansing Smith produce?
Lansing Smith reported 3,747,743 MWh (3.75 TWh) of net generation in 2025, a 64.7% capacity factor on 661.5 MW of nameplate capacity. From January to July 2026 it reported 2.09 TWh, which is provisional.
Where is Lansing Smith?
Lansing Smith is in Bay County, Florida, at 30.2686, −85.7003. It is in the Florida Power & Light Company balancing area (FPL).
Who operates Lansing Smith?
EIA-860M for August 2026 lists Florida Power & Light Co as the operator (EIA operator ID 6452). The operator is not always the owner.
When did Lansing Smith start operating?
Its first generator began operating in May 1971, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
- EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page