Key facts

Capacity
2.1 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
January 1968First generator online
Operator
Ketchikan Public UtilitiesEIA operator ID 10210
Grid
Not reported
Price nodes
None linkedNo verified ISO node
Location
Ketchikan Gateway, AK55.3814, −131.5178
EIA plant ID
6581EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Silvis produces

Free · EIA-923

Net generation, 2025

14.3 GWh

14,316 MWh, final

Capacity factor, 2025

77.8%

2024: 15.1%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

2.8–14.5

GWh a year. Low 2024, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
200113,968Not reported12 of 12
20029,954Not reported12 of 12
200313,629Not reported12 of 12
200412,421Not reported12 of 12
200512,516Not reported12 of 12
200612,845Not reported12 of 12
200711,813Not reported12 of 12
200813,177Not reported12 of 12
200912,139Not reported12 of 12
201011,36861.8%12 of 12
201112,87170.0%12 of 12
201213,74574.5%12 of 12
201310,99759.8%12 of 12
201413,72374.6%12 of 12
201513,60774.0%12 of 12
201613,20771.6%12 of 12
201710,11055.0%12 of 12
20189,22150.1%12 of 12
20198,56046.5%12 of 12
202013,61473.8%12 of 12
202114,46278.6%12 of 12
202212,35267.1%12 of 12
202311,46062.3%12 of 12
20242,78015.1%12 of 12
202514,31677.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric2.1January 1968

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Ketchikan Public Utilities as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Silvis and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Silvis

More plants operated by Ketchikan Public Utilities

Questions about Silvis

How much power does Silvis produce?

Silvis reported 14,316 MWh (14.3 GWh) of net generation in 2025, a 77.8% capacity factor on 2.1 MW of nameplate capacity.

Where is Silvis?

Silvis is in Ketchikan Gateway, Alaska, at 55.3814, −131.5178.

Who operates Silvis?

EIA-860M for August 2026 lists Ketchikan Public Utilities as the operator (EIA operator ID 10210). The operator is not always the owner.

When did Silvis start operating?

Its first generator began operating in January 1968, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page