SolarBattery storageOperatingERCOT

Gaia Hybrid

Solar and battery storage project in Navarro County, Texas. 229.5 MW of nameplate capacity across 2 generators, operated by Sunraycer Assets I LLC.

Also known as EIA plant 66342

This project groups Gaia Hybrid (EIA 66342). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Trinidad (TX)Fence Post Solar Hybrid Project, LLCWAL565Pauline BESSGaia Hybrid10 km
Open in the map
6 plants within 31 km, from EIA coordinates.

Key facts

Capacity
229.5 MWSolar 152.7 · Battery storage 76.8
Generators
2 operatingEIA-860M, August 2026
Operating since
July 2026First generator online
Operator
Sunraycer Assets I LLCEIA operator ID 65815
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Navarro County, TX32.1608, −96.1953
EIA plant ID
66342EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Gaia Hybrid produces

Free · EIA-923

Net generation, 2025

Not reported

Not reported MWh, final. 0 of 12 months reported

Capacity factor, 2025

Not reported

2024: Not reported

January to July 2026

111 GWh

Provisional. 4 of 7 months reported

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024Not reportedNot reported0 of 12
2025Not reportedNot reported0 of 12
2026 (provisional, partial year)111,384Not reported4 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GAIABBatteries76.8July 2026
GAIASSolar Photovoltaic152.7July 2026

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Sunraycer Assets I LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Gaia Hybrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Gaia Hybrid

More plants operated by Sunraycer Assets I LLC

Questions about Gaia Hybrid

Where is Gaia Hybrid?

Gaia Hybrid is in Navarro County, Texas, at 32.1608, −96.1953. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Gaia Hybrid?

EIA-860M for August 2026 lists Sunraycer Assets I LLC as the operator (EIA operator ID 65815). The operator is not always the owner.

Is Gaia Hybrid a solar or a battery storage plant?

Both. Solar capacity totals 152.7 MW and battery storage capacity totals 76.8 MW.

When did Gaia Hybrid start operating?

Its first generator began operating in July 2026, according to EIA-860M.

Does InfraMap have power prices for Gaia Hybrid?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Gaia Hybrid, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page