Roadrunner Crossing Energy Storage
Battery storage project in Eastland County, Texas. 150 MW of nameplate capacity across 1 generator, operated by Roadrunner Crossing Energy Storage LLC.
Also known as EIA plant 68460
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 150 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- December 2025First generator online
- Operator
- Roadrunner Crossing Energy Storage LLCEIA operator ID 66821
- Grid
- ERCOTBalancing authority ERCO
- Price nodes
- 1 ERCOT nodeResource nodes with prices
- Location
- Eastland County, TX32.4142, −99.1077
- EIA plant ID
- 68460EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Roadrunner Crossing Energy Storage produces
Free · EIA-923Net generation, 2025
0 MWh
0 MWh, final. 1 of 12 months reported
Battery discharge, 2025
0 MWh
Charge 0 MWh
January to July 2026
−11.7 GWh
Provisional
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | Not reported | Not reported | 0 of 12 |
| 2022 | Not reported | Not reported | 0 of 12 |
| 2023 | Not reported | Not reported | 0 of 12 |
| 2024 | Not reported | Not reported | 0 of 12 |
| 2025 | 0 | Not reported | 1 of 12 |
| 2026 (provisional, partial year) | −11,671 | Not reported | 7 of 7 |
* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.
Power prices and basis
Free account · ERCOTEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 7137 | Batteries | 150.0 | December 2025 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Roadrunner Crossing Energy Storage LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
300 analyst questions a month, plus MCP
Query Roadrunner Crossing Energy Storage and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Roadrunner Crossing Energy Storage
Questions about Roadrunner Crossing Energy Storage
How much power does Roadrunner Crossing Energy Storage produce?
Roadrunner Crossing Energy Storage reported 0 MWh (0 MWh) of net generation in 2025. From January to July 2026 it reported −11.7 GWh, which is provisional. 1 of 12 months were reported for 2025.
Where is Roadrunner Crossing Energy Storage?
Roadrunner Crossing Energy Storage is in Eastland County, Texas, at 32.4142, −99.1077. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).
Who operates Roadrunner Crossing Energy Storage?
EIA-860M for August 2026 lists Roadrunner Crossing Energy Storage LLC as the operator (EIA operator ID 66821). The operator is not always the owner.
When did Roadrunner Crossing Energy Storage start operating?
Its first generator began operating in December 2025, according to EIA-860M.
Does InfraMap have power prices for Roadrunner Crossing Energy Storage?
Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Roadrunner Crossing Energy Storage, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page