Natural gasOperatingTAL

S O Purdom

Natural gas power plant in Wakulla County, Florida. 270.1 MW of nameplate capacity across 2 generators, operated by City of Tallahassee - (FL).

Also known as S O Purdom Power Plant · S.O. Purdom · SO Purdom · EIA plant 689

Analyst: free account, 1 question a day.

FL Solar 4, LLCFL Solar D2, LLCCoTAL Solar FarmSub 12Arvah B HopkinsS O Purdom20 km
Open in the map
5 plants within 37 km, from EIA coordinates.

Key facts

Capacity
270.1 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
July 2000First generator online
Operator
City of Tallahassee - (FL)EIA operator ID 18445
Grid
TALBalancing authority TAL
Price nodes
None linkedNo verified ISO node
Location
Wakulla County, FL30.1623, −84.2007
EIA plant ID
689EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power S O Purdom produces

Free · EIA-923

Net generation, 2025

1.38 TWh

1,383,380 MWh, final

Capacity factor, 2025

58.5%

2024: 50.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.9–1.4

TWh a year. Low 2016, high 2023

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000570,171Not reported12 of 12
20011,566,742Not reported12 of 12
20021,623,738Not reported12 of 12
20031,203,551Not reported9 of 12
20041,105,657Not reported12 of 12
20051,571,567Not reported12 of 12
20061,736,142Not reported12 of 12
20071,448,602Not reported12 of 12
20081,450,886Not reported12 of 12
2009632,633Not reported6 of 12
2010862,65340.0%9 of 12
20111,328,26346.4%12 of 12
20121,068,06337.2%12 of 12
20131,097,993Not reported12 of 12
2014118,11957.3%1 of 12
20151,327,01054.7%12 of 12
2016904,19137.2%12 of 12
20171,250,741Not reported12 of 12
2018967,818Not reported10 of 12
20191,300,16755.0%12 of 12
20201,033,96043.6%12 of 12
20211,338,59056.6%12 of 12
20221,354,94157.3%12 of 12
20231,394,75258.9%12 of 12
20241,206,31250.8%12 of 12
20251,383,38058.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

647,224

US short tons. 2024: 560,603

SO₂, 2025

3

US short tons

NOx, 2025

162

US short tons

CO₂ per MWh, calculated

0.47 t

About 936 lb per MWh

1 of 1 EPA units reported CO₂ in 2025 (7, 8), matched to EIA plant 689 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

68

million gallons

Consumption, 2024

68

million gallons

Source

ST. MARKS RIVER

Surface, Brackish. Induced-draft tower

Watershed stress

Very low/none · 0.116

USGS SUI, HUC12 Moriah Creek-Saint Marks River

12 of 12 cooling months report withdrawal. Saline, brackish or ocean intake; not tested. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
8Natural Gas Fired Combined Cycle180.0July 2000
9Natural Gas Fired Combined Cycle90.1July 2000

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Tallahassee - (FL) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query S O Purdom and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near S O Purdom

More plants operated by City of Tallahassee - (FL)

Questions about S O Purdom

How much power does S O Purdom produce?

S O Purdom reported 1,383,380 MWh (1.38 TWh) of net generation in 2025, a 58.5% capacity factor on 270.1 MW of nameplate capacity.

Where is S O Purdom?

S O Purdom is in Wakulla County, Florida, at 30.1623, −84.2007. It is in the City of Tallahassee balancing area (TAL).

Who operates S O Purdom?

EIA-860M for August 2026 lists City of Tallahassee - (FL) as the operator (EIA operator ID 18445). The operator is not always the owner.

When did S O Purdom start operating?

Its first generator began operating in July 2000, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values