Battery storageOperatingMISO

Blount BESS

Battery storage project in Dane County, Wisconsin. 7 MW of nameplate capacity across 1 generator, operated by Madison Gas & Electric Co.

Also known as EIA plant 69311

Analyst: free account, 1 question a day.

UW Madison Charter Street PlantGalactic WindNine SpringsBlount BESS2 km
Open in the map
6 plants within 4.7 km, from EIA coordinates.

Key facts

Capacity
7 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 2026First generator online
Operator
Madison Gas & Electric CoEIA operator ID 11479
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Dane County, WI43.0789, −89.3739
EIA plant ID
69311EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Blount BESS produces

Free · EIA-923

EIA-923 has no net generation reported for this plant.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BLTBBatteries7.0April 2026

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Madison Gas & Electric Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Blount BESS and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Blount BESS

More plants operated by Madison Gas & Electric Co

Questions about Blount BESS

Where is Blount BESS?

Blount BESS is in Dane County, Wisconsin, at 43.0789, −89.3739. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Blount BESS?

EIA-860M for August 2026 lists Madison Gas & Electric Co as the operator (EIA operator ID 11479). The operator is not always the owner.

When did Blount BESS start operating?

Its first generator began operating in April 2026, according to EIA-860M.

Does InfraMap have power prices for Blount BESS?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Blount BESS, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page