Power plants in Richmond County, Georgia
8 operating power plants in Richmond County, Georgia, with 128 MW of nameplate capacity, largest first. From EIA-860M, August 2026.
Plants
8
Nameplate capacity
128 MW
Net generation, 2025
79.9 GWh
7 of 8 plants reported
Largest power plants in Richmond County
| # | Plant | MW | GWh, 2025 | Capacity factor |
|---|---|---|---|---|
| 1 | Clearwater Paper Corporation - AugustaWood biomass and natural gas | 85 | – | – |
| 2 | Fort Gordon Solar FacilitySolar | 30 | 51.4 | 19.6% |
| 3 | Richmond County GA S2 LLCSolar | 3.0 | 6.2 | 23.5% |
| 4 | ApalachicolaSolar | 2.5 | 4.8 | 22.1% |
| 5 | Richmond Hayes SolarSolar | 2.3 | 3.1 | 15.5% |
| 6 | King MillHydro | 2.2 | 3.7 | 19.4% |
| 7 | Sibley MillHydro | 2.1 | 8.0 | 43.4% |
| 8 | Graniteville Enterprise DivisionHydro | 1.2 | 2.6 | 24.5% |
MW is the nameplate capacity of operating generators and batteries. Source: EIA-860M August 2026, published 2026-09-24, and EIA-923 2025. Page updated 2026-10-04. Data sources
More power plant lists for Georgia
Largest power plants in Georgia50 plants · 37,632 MWSolar farms in Georgia154 plants · 5,496 MWBattery storage projects in Georgia9 projects · 864 MWNatural gas power plants in Georgia33 plants · 18,526 MWCoal power plants in Georgia2 plants · 6,172 MWNuclear power plants in Georgia2 plants · 6,506 MWHydroelectric power plants in Georgia29 plants · 1,877 MW