Northeast (MI)
Natural gas and oil power plant in Macomb County, Michigan. 113.8 MW of nameplate capacity across 6 generators, operated by DTE Electric Company.
Also known as EIA plant 1734
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 113.8 MWNatural gas 71.4 · Oil 42.4
- Generators
- 6 operatingEIA-860M, August 2026
- Operating since
- May 1966First generator online
- Operator
- DTE Electric CompanyEIA operator ID 5109
- Grid
- MISOBalancing authority MISO
- Price nodes
- 3 MISO nodesResource nodes with prices
- Location
- Macomb County, MI42.4500, −83.0381
- EIA plant ID
- 1734EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Northeast (MI) produces
Free · EIA-923Net generation, 2025
14.8 GWh
14,796 MWh, final
Capacity factor, 2025
1.5%
2024: 0.6%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
0.2–14.8
GWh a year. Low 2015, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | 29,390 | Not reported | 12 of 12 |
| 2001 | 10,166 | Not reported | 12 of 12 |
| 2002 | 2,396 | Not reported | 12 of 12 |
| 2003 | 4,373 | Not reported | 11 of 12 |
| 2004 | 516 | Not reported | 12 of 12 |
| 2005 | 3,760 | Not reported | 12 of 12 |
| 2006 | 2,545 | Not reported | 12 of 12 |
| 2007 | 1,980 | Not reported | 12 of 12 |
| 2008 | 88 | Not reported | 12 of 12 |
| 2009 | −1,427 | Not reported | 12 of 12 |
| 2010 | 842 | 0.1% | 12 of 12 |
| 2011 | 1,469 | 0.1% | 12 of 12 |
| 2012 | 313 | 0.0% | 12 of 12 |
| 2013 | 528 | 0.0% | 12 of 12 |
| 2014 | 490 | 0.0% | 12 of 12 |
| 2015 | 190 | 0.0% | 12 of 12 |
| 2016 | 1,160 | Not reported | 12 of 12 |
| 2017 | 2,670 | 0.2% | 12 of 12 |
| 2018 | 6,556 | 0.6% | 12 of 12 |
| 2019 | 1,090 | 0.1% | 12 of 12 |
| 2020 | 2,434 | 0.2% | 12 of 12 |
| 2021 | 10,225 | 0.9% | 12 of 12 |
| 2022 | 8,339 | 0.7% | 12 of 12 |
| 2023 | 1,796 | 0.2% | 12 of 12 |
| 2024 | 5,858 | 0.6% | 12 of 12 |
| 2025 | 14,796 | 1.5% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · MISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 2 | Natural Gas Fired Combustion Turbine | 16.0 | June 1966 |
| 3 | Natural Gas Fired Combustion Turbine | 16.0 | May 1966 |
| 4 | Natural Gas Fired Combustion Turbine | 16.0 | May 1966 |
| 5 | Natural Gas Fired Combustion Turbine | 23.4 | June 1971 |
| 6 | Petroleum Liquids | 21.2 | May 1971 |
| 7 | Petroleum Liquids | 21.2 | May 1971 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists DTE Electric Company as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Northeast (MI) and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Northeast (MI)
More plants operated by DTE Electric Company
Questions about Northeast (MI)
How much power does Northeast (MI) produce?
Northeast (MI) reported 14,796 MWh (14.8 GWh) of net generation in 2025, a 1.5% capacity factor on 113.8 MW of nameplate capacity.
Where is Northeast (MI)?
Northeast (MI) is in Macomb County, Michigan, at 42.4500, −83.0381. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Northeast (MI)?
EIA-860M for August 2026 lists DTE Electric Company as the operator (EIA operator ID 5109). The operator is not always the owner.
Is Northeast (MI) a natural gas or a oil plant?
Both. Natural gas capacity totals 71.4 MW and oil capacity totals 42.4 MW.
When did Northeast (MI) start operating?
Its first generator began operating in May 1966, according to EIA-860M.
Does InfraMap have power prices for Northeast (MI)?
Yes. InfraMap has MISO day-ahead and real-time prices at 3 price nodes linked to Northeast (MI), with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page