Natural gasOperatingMISO

St Clair

Natural gas power plant in St Clair County, Michigan. 18.5 MW of nameplate capacity across 1 generator, operated by DTE Electric Company.

Also known as Saint Clair Power Plant · EIA plant 1743

Analyst: free account, 1 question a day.

Belle RiverCargill SaltBlue Water Renewables IncSt Clair10 km
Open in the map
6 plants within 22 km, from EIA coordinates.

Key facts

Capacity
18.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 1968First generator online
Operator
DTE Electric CompanyEIA operator ID 5109
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
St Clair County, MI42.7642, −82.4719
EIA plant ID
1743EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power St Clair produces

Free · EIA-923

Net generation, 2025

Not reported

Not reported MWh, final. 0 of 12 months reported

Capacity factor, 2025

Not reported

2024: Not reported

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2021

3.2–5.4

TWh a year. Low 2021, high 2015

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20007,357,188Not reported12 of 12
20015,764,277Not reported12 of 12
20026,965,078Not reported12 of 12
20036,705,759Not reported12 of 12
20047,387,066Not reported12 of 12
20057,378,682Not reported12 of 12
20067,439,052Not reported12 of 12
20077,614,925Not reported12 of 12
20083,575,996Not reported6 of 12
20096,574,360Not reported12 of 12
20106,786,64249.3%12 of 12
20116,135,56744.6%12 of 12
20125,427,43339.3%12 of 12
20131,076,59546.8%2 of 12
2014Not reportedNot reported0 of 12
20155,446,47039.6%12 of 12
20163,678,674Not reported12 of 12
20173,548,033Not reported12 of 12
20184,530,895Not reported12 of 12
20193,900,957Not reported12 of 12
2020Not reportedNot reported0 of 12
20213,220,44229.8%12 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024−93Not reported6 of 12
2025Not reportedNot reported0 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

CO₂, 2022

1.87M

US short tons. 2021: 3.87M

SO₂, 2022

6,273

US short tons

NOx, 2022

1,761

US short tons

4 of 4 EPA units reported CO₂ in 2022 (1, 2, 3, 4, 6, 7), matched to EIA plant 1743 through the EPA–EIA crosswalk.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
11Natural Gas Fired Combustion Turbine18.5May 1968

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists DTE Electric Company as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query St Clair and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near St Clair

More plants operated by DTE Electric Company

Questions about St Clair

Where is St Clair?

St Clair is in St Clair County, Michigan, at 42.7642, −82.4719. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates St Clair?

EIA-860M for August 2026 lists DTE Electric Company as the operator (EIA operator ID 5109). The operator is not always the owner.

When did St Clair start operating?

Its first generator began operating in May 1968, according to EIA-860M.

Does InfraMap have power prices for St Clair?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to St Clair, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page