Chestnut Ridge Gas Recovery
Landfill gas power plant in Anderson County, Tennessee. 4.8 MW of nameplate capacity across 5 generators, operated by WM Renewable Energy LLC.
Also known as EIA plant 50570
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 4.8 MWNameplate
- Generators
- 5 operatingEIA-860M, August 2026
- Operating since
- January 1992First generator online
- Operator
- WM Renewable Energy LLCEIA operator ID 54842
- Grid
- TVABalancing authority TVA
- Price nodes
- None linkedNo verified ISO node
- Location
- Anderson County, TN36.1172, −84.0317
- EIA plant ID
- 50570EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Chestnut Ridge Gas Recovery produces
Free · EIA-923Net generation, 2025
34.0 GWh
33,962 MWh, final
Capacity factor, 2025
80.8%
2024: 73.7%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
22.3–34.0
GWh a year. Low 2022, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | 23,660 | Not reported | 12 of 12 |
| 2002 | 22,646 | Not reported | 12 of 12 |
| 2003 | 19,186 | Not reported | 12 of 12 |
| 2004 | 12,033 | Not reported | 12 of 12 |
| 2005 | 23,571 | Not reported | 12 of 12 |
| 2006 | 23,675 | Not reported | 12 of 12 |
| 2007 | 19,228 | Not reported | 12 of 12 |
| 2008 | 22,505 | Not reported | 12 of 12 |
| 2009 | 23,249 | Not reported | 12 of 12 |
| 2010 | 19,262 | 68.7% | 12 of 12 |
| 2011 | 20,487 | Not reported | 12 of 12 |
| 2012 | 25,152 | 59.7% | 12 of 12 |
| 2013 | 31,663 | 75.3% | 12 of 12 |
| 2014 | 33,641 | 80.0% | 12 of 12 |
| 2015 | 31,521 | 75.0% | 12 of 12 |
| 2016 | 33,938 | 80.5% | 12 of 12 |
| 2017 | 30,882 | 73.4% | 12 of 12 |
| 2018 | 29,794 | 70.9% | 12 of 12 |
| 2019 | 27,264 | 64.8% | 12 of 12 |
| 2020 | 31,866 | 75.6% | 12 of 12 |
| 2021 | 23,056 | 54.8% | 12 of 12 |
| 2022 | 22,336 | Not reported | 12 of 12 |
| 2023 | Not reported | Not reported | 0 of 12 |
| 2024 | 31,088 | 73.7% | 12 of 12 |
| 2025 | 33,962 | 80.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| GEN1 | Landfill Gas | 0.8 | January 1992 |
| GEN2 | Landfill Gas | 0.8 | January 1992 |
| GEN3 | Landfill Gas | 0.8 | January 1992 |
| GEN4 | Landfill Gas | 0.8 | January 1992 |
| GEN5 | Landfill Gas | 1.6 | November 2011 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists WM Renewable Energy LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Chestnut Ridge Gas Recovery and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Chestnut Ridge Gas Recovery
More plants operated by WM Renewable Energy LLC
Questions about Chestnut Ridge Gas Recovery
How much power does Chestnut Ridge Gas Recovery produce?
Chestnut Ridge Gas Recovery reported 33,962 MWh (34.0 GWh) of net generation in 2025, a 80.8% capacity factor on 4.8 MW of nameplate capacity.
Where is Chestnut Ridge Gas Recovery?
Chestnut Ridge Gas Recovery is in Anderson County, Tennessee, at 36.1172, −84.0317. It is in the Tennessee Valley Authority balancing area (TVA).
Who operates Chestnut Ridge Gas Recovery?
EIA-860M for August 2026 lists WM Renewable Energy LLC as the operator (EIA operator ID 54842). The operator is not always the owner.
When did Chestnut Ridge Gas Recovery start operating?
Its first generator began operating in January 1992, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page