HydroOperatingTVA

Fort Loudoun

Hydro power plant in Loudon County, Tennessee. 153.3 MW of nameplate capacity across 4 generators, operated by Tennessee Valley Authority.

Also known as Fort Loudon Hydro · EIA plant 3402

Analyst: free account, 1 question a day.

Primient Loudon PlantMelton HillSR Blount, LLCSR MaryvilleKingstonFort Loudoun10 km
Open in the map
6 plants within 30 km, from EIA coordinates.

Key facts

Capacity
153.3 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
November 1943First generator online
Operator
Tennessee Valley AuthorityEIA operator ID 18642
Grid
TVABalancing authority TVA
Price nodes
None linkedNo verified ISO node
Location
Loudon County, TN35.7917, −84.2431
EIA plant ID
3402EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Fort Loudoun produces

Free · EIA-923

Net generation, 2025

633 GWh

633,112 MWh, final

Capacity factor, 2025

47.1%

2024: 54.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.6–1.3

TWh a year. Low 2016, high 2020

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000548,963Not reported12 of 12
2001546,364Not reported12 of 12
2002590,698Not reported12 of 12
2003970,387Not reported12 of 12
2004875,635Not reported12 of 12
2005804,195Not reported12 of 12
2006672,228Not reported12 of 12
2007390,677Not reported12 of 12
2008451,470Not reported12 of 12
2009809,534Not reported12 of 12
2010686,129Not reported12 of 12
2011823,12261.3%12 of 12
2012721,21853.6%12 of 12
2013936,25669.7%12 of 12
2014727,28254.2%12 of 12
2015810,55360.4%12 of 12
2016595,93444.3%12 of 12
2017733,40754.6%12 of 12
2018913,24068.0%12 of 12
2019932,12969.4%12 of 12
20201,264,51093.9%12 of 12
2021940,35570.0%12 of 12
2022778,70658.0%12 of 12
2023676,50850.4%12 of 12
2024732,06354.4%12 of 12
2025633,11247.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric35.5January 1944
2Conventional Hydroelectric34.2November 1943
3Conventional Hydroelectric43.0October 1948
4Conventional Hydroelectric40.6January 1949

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Tennessee Valley Authority as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Fort Loudoun and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Fort Loudoun

More plants operated by Tennessee Valley Authority

Questions about Fort Loudoun

How much power does Fort Loudoun produce?

Fort Loudoun reported 633,112 MWh (633 GWh) of net generation in 2025, a 47.1% capacity factor on 153.3 MW of nameplate capacity.

Where is Fort Loudoun?

Fort Loudoun is in Loudon County, Tennessee, at 35.7917, −84.2431. It is in the Tennessee Valley Authority balancing area (TVA).

Who operates Fort Loudoun?

EIA-860M for August 2026 lists Tennessee Valley Authority as the operator (EIA operator ID 18642). The operator is not always the owner.

When did Fort Loudoun start operating?

Its first generator began operating in November 1943, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page