Clearwater Paper APP CB
Wood biomass power plant in Desha County, Arkansas. 28 MW of nameplate capacity across 1 generator, operated by Clearwater Paper Corporation.
Also known as Clearwater Paper Cogen · EIA plant 50638
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 28 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- November 1977First generator online
- Operator
- Clearwater Paper CorporationEIA operator ID 56225
- Grid
- MISOBalancing authority MISO
- Price nodes
- None linkedNo verified ISO node
- Location
- Desha County, AR33.7061, −91.2371
- EIA plant ID
- 50638EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Clearwater Paper APP CB produces
Free · EIA-923Net generation, 2025
123 GWh
123,252 MWh, final
Capacity factor, 2025
50.2%
2024: 51.3%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
93.1–126.2
GWh a year. Low 2017, high 2024
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | 157,391 | Not reported | 10 of 12 |
| 2002 | 123,460 | Not reported | 12 of 12 |
| 2003 | 0 | Not reported | 9 of 12 |
| 2004 | 166,222 | Not reported | 12 of 12 |
| 2005 | 145,291 | Not reported | 12 of 12 |
| 2006 | 146,022 | Not reported | 12 of 12 |
| 2007 | 149,672 | Not reported | 12 of 12 |
| 2008 | 165,645 | Not reported | 12 of 12 |
| 2009 | 170,202 | Not reported | 12 of 12 |
| 2010 | 163,373 | 93.2% | 12 of 12 |
| 2011 | 159,909 | 91.3% | 12 of 12 |
| 2012 | 167,320 | 95.2% | 12 of 12 |
| 2013 | 120,204 | Not reported | 12 of 12 |
| 2014 | 119,227 | 68.1% | 12 of 12 |
| 2015 | 109,626 | 62.6% | 12 of 12 |
| 2016 | 99,202 | Not reported | 12 of 12 |
| 2017 | 93,055 | 37.9% | 12 of 12 |
| 2018 | 114,545 | 46.7% | 12 of 12 |
| 2019 | 114,107 | 46.5% | 12 of 12 |
| 2020 | 116,511 | 47.4% | 12 of 12 |
| 2021 | 114,300 | 46.6% | 12 of 12 |
| 2022 | 101,062 | 41.2% | 12 of 12 |
| 2023 | 110,715 | 45.1% | 12 of 12 |
| 2024 | 126,158 | 51.3% | 12 of 12 |
| 2025 | 123,252 | 50.2% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| GEN1 | Wood/Wood Waste Biomass | 28.0 | November 1977 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Clearwater Paper Corporation as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Clearwater Paper APP CB and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Clearwater Paper APP CB
More plants operated by Clearwater Paper Corporation
Questions about Clearwater Paper APP CB
How much power does Clearwater Paper APP CB produce?
Clearwater Paper APP CB reported 123,252 MWh (123 GWh) of net generation in 2025, a 50.2% capacity factor on 28 MW of nameplate capacity.
Where is Clearwater Paper APP CB?
Clearwater Paper APP CB is in Desha County, Arkansas, at 33.7061, −91.2371. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Clearwater Paper APP CB?
EIA-860M for August 2026 lists Clearwater Paper Corporation as the operator (EIA operator ID 56225). The operator is not always the owner.
When did Clearwater Paper APP CB start operating?
Its first generator began operating in November 1977, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page