Key facts

Capacity
12.3 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
December 1985First generator online
Operator
Eagle Creek Renewable Energy, LLCEIA operator ID 57280
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Passaic County, NJ40.9153, −74.1810
EIA plant ID
52068EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Great Falls Hydro Project produces

Free · EIA-923

Net generation, 2025

6.34 GWh

6,342 MWh, final

Capacity factor, 2025

5.9%

2024: 3.3%

January to July 2026

0 MWh

Provisional

Range, 2015 to 2025

3.5–35.5

GWh a year. Low 2024, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200118,001Not reported12 of 12
20028,010Not reported12 of 12
200327,748Not reported12 of 12
200426,837Not reported12 of 12
200521,821Not reported12 of 12
200626,623Not reported12 of 12
200717,052Not reported12 of 12
200822,412Not reported12 of 12
200927,409Not reported12 of 12
201018,11919.2%12 of 12
201124,40725.8%12 of 12
201210,75511.3%12 of 12
201318,27419.3%12 of 12
201417,296Not reported12 of 12
20159,5418.9%12 of 12
20169,4788.8%12 of 12
201713,63312.7%12 of 12
201835,53833.0%12 of 12
201926,46824.6%12 of 12
202015,35614.2%12 of 12
202118,22416.9%12 of 12
20225,2264.9%12 of 12
202311,61610.8%12 of 12
20243,5413.3%12 of 12
20256,3425.9%12 of 12
2026 (provisional, partial year)00.0%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Conventional Hydroelectric4.1December 1985
GEN2Conventional Hydroelectric4.1December 1985
GEN3Conventional Hydroelectric4.1December 1985

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Eagle Creek Renewable Energy, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Great Falls Hydro Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Great Falls Hydro Project

More plants operated by Eagle Creek Renewable Energy, LLC

Questions about Great Falls Hydro Project

How much power does Great Falls Hydro Project produce?

Great Falls Hydro Project reported 6,342 MWh (6.34 GWh) of net generation in 2025, a 5.9% capacity factor on 12.3 MW of nameplate capacity. From January to July 2026 it reported 0 MWh, which is provisional.

Where is Great Falls Hydro Project?

Great Falls Hydro Project is in Passaic County, New Jersey, at 40.9153, −74.1810. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Great Falls Hydro Project?

EIA-860M for August 2026 lists Eagle Creek Renewable Energy, LLC as the operator (EIA operator ID 57280). The operator is not always the owner.

When did Great Falls Hydro Project start operating?

Its first generator began operating in December 1985, according to EIA-860M.

Does InfraMap have power prices for Great Falls Hydro Project?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Great Falls Hydro Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page