Warner Lambert
Natural gas power plant in Washtenaw County, Michigan. 3 MW of nameplate capacity across 1 generator, operated by University of Michigan NCampus Research.
Also known as EIA plant 54604
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 3 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- August 1989First generator online
- Operator
- University of Michigan NCampus ResearchEIA operator ID 56478
- Grid
- MISOBalancing authority MISO
- Price nodes
- None linkedNo verified ISO node
- Location
- Washtenaw County, MI42.2993, −83.7053
- EIA plant ID
- 54604EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Warner Lambert produces
Free · EIA-923Net generation, 2025
24.3 GWh
24,329 MWh, final
Capacity factor, 2025
22.4%
2024: 21.3%
January to July 2026
14.6 GWh
Provisional
Range, 2016 to 2025
19.3–25.0
GWh a year. Low 2023, high 2018
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | 25,047 | Not reported | 12 of 12 |
| 2002 | 22,667 | Not reported | 12 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | 24,747 | Not reported | 12 of 12 |
| 2005 | 25,533 | Not reported | 12 of 12 |
| 2006 | 459 | Not reported | 12 of 12 |
| 2007 | 1,162 | Not reported | 12 of 12 |
| 2008 | 11 | Not reported | 1 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | 28 | 0.0% | 12 of 12 |
| 2011 | 10 | Not reported | 12 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | 5,935 | 5.5% | 12 of 12 |
| 2014 | 24,315 | 22.4% | 12 of 12 |
| 2015 | 2,489 | 27.0% | 1 of 12 |
| 2016 | 24,967 | 22.9% | 12 of 12 |
| 2017 | 24,468 | 22.5% | 12 of 12 |
| 2018 | 25,002 | 23.0% | 12 of 12 |
| 2019 | 23,802 | 21.9% | 12 of 12 |
| 2020 | 24,166 | 22.2% | 12 of 12 |
| 2021 | 19,564 | 21.6% | 10 of 12 |
| 2022 | 20,857 | 20.9% | 11 of 12 |
| 2023 | 19,335 | 17.8% | 12 of 12 |
| 2024 | 23,206 | 21.3% | 12 of 12 |
| 2025 | 24,329 | 22.4% | 12 of 12 |
| 2026 (provisional, partial year) | 14,625 | 23.2% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 5164 | Natural Gas Fired Combustion Turbine | 3.0 | August 1989 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists University of Michigan NCampus Research as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Warner Lambert and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Warner Lambert
Questions about Warner Lambert
How much power does Warner Lambert produce?
Warner Lambert reported 24,329 MWh (24.3 GWh) of net generation in 2025, a 22.4% capacity factor on 3 MW of nameplate capacity. From January to July 2026 it reported 14.6 GWh, which is provisional.
Where is Warner Lambert?
Warner Lambert is in Washtenaw County, Michigan, at 42.2993, −83.7053. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Warner Lambert?
EIA-860M for August 2026 lists University of Michigan NCampus Research as the operator (EIA operator ID 56478). The operator is not always the owner.
When did Warner Lambert start operating?
Its first generator began operating in August 1989, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page