Natural gasOperatingSPP

Green Country Power Station

Natural gas power plant in Tulsa County, Oklahoma. 903.9 MW of nameplate capacity across 6 generators, operated by Public Service Co of Oklahoma.

Also known as Green Country Energy · EIA plant 55146

Analyst: free account, 1 question a day.

TulsaOneta Energy CenterTulsa LFG LLCGreen Country20 km
Open in the map
5 plants within 34 km, from EIA coordinates.

Key facts

Capacity
903.9 MWNameplate
Generators
6 operatingEIA-860M, August 2026
Operating since
February 2002First generator online
Operator
Public Service Co of OklahomaEIA operator ID 15474
Grid
SPPBalancing authority SWPP
Price nodes
3 SPP nodesResource nodes with prices
Location
Tulsa County, OK35.9833, −95.9346
EIA plant ID
55146EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Green Country produces

Free · EIA-923

Net generation, 2025

3.65 TWh

3,651,548 MWh, final

Capacity factor, 2025

46.1%

2024: 53.5%

January to July 2026

2.39 TWh

Provisional

Range, 2015 to 2025

3.2–5.0

TWh a year. Low 2022, high 2018

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
20022,105,160Not reported12 of 12
20032,136,922Not reported12 of 12
20042,323,460Not reported12 of 12
20052,889,638Not reported12 of 12
20062,701,435Not reported12 of 12
20073,060,126Not reported12 of 12
20083,189,139Not reported12 of 12
20093,752,218Not reported12 of 12
20102,485,85031.4%12 of 12
20112,181,12727.5%12 of 12
20124,017,22350.6%12 of 12
20133,164,51440.0%12 of 12
20143,127,41939.5%12 of 12
20153,734,50447.2%12 of 12
20163,928,37649.5%12 of 12
20174,928,96162.2%12 of 12
20184,985,80963.0%12 of 12
20194,725,79759.7%12 of 12
20204,240,31153.4%12 of 12
20213,332,68742.1%12 of 12
20223,172,91540.1%12 of 12
20233,853,69948.7%12 of 12
20244,245,66253.5%12 of 12
20253,651,54846.1%12 of 12
2026 (provisional, partial year)2,388,67551.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

CO₂, 2025

1.57M

US short tons. 2024: 1.83M

SO₂, 2025

8

US short tons

NOx, 2025

373

US short tons

CO₂ per MWh, calculated

0.43 t

About 861 lb per MWh

3 of 3 EPA units reported CO₂ in 2025 (CTGEN1, CTGEN2, CTGEN3), matched to EIA plant 55146 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

1,140

million gallons

Consumption, 2024

1,030

million gallons

Source

Municipal

Other, Other. Induced-draft tower

Watershed stress

Moderate · 0.485

USGS SUI, HUC12 Posey Creek-Arkansas River

36 of 36 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CTG1Natural Gas Fired Combined Cycle179.3February 2002
CTG2Natural Gas Fired Combined Cycle179.3February 2002
CTG3Natural Gas Fired Combined Cycle179.3February 2002
STG1Natural Gas Fired Combined Cycle122.0February 2002
STG2Natural Gas Fired Combined Cycle122.0February 2002
STG3Natural Gas Fired Combined Cycle122.0February 2002

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Public Service Co of Oklahoma as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Green Country Power Station and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Green Country

More plants operated by Public Service Co of Oklahoma

Questions about Green Country

How much power does Green Country Power Station produce?

Green Country Power Station reported 3,651,548 MWh (3.65 TWh) of net generation in 2025, a 46.1% capacity factor on 903.9 MW of nameplate capacity. From January to July 2026 it reported 2.39 TWh, which is provisional.

Where is Green Country Power Station?

Green Country Power Station is in Tulsa County, Oklahoma, at 35.9833, −95.9346. It is in the Southwest Power Pool balancing area (SWPP).

Who operates Green Country Power Station?

EIA-860M for August 2026 lists Public Service Co of Oklahoma as the operator (EIA operator ID 15474). The operator is not always the owner.

When did Green Country Power Station start operating?

Its first generator began operating in February 2002, according to EIA-860M.

Does InfraMap have power prices for Green Country Power Station?

Yes. InfraMap has SPP day-ahead and real-time prices at 3 price nodes linked to Green Country Power Station, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page